Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
The Sensible Resurgence of the Multigenerational Home
August 13, 2014 —
Chris Farrell – BloombergOne of the biggest fears spawned by the recession and subsequent up-and-down recovery is getting stuck at home. The commonly expressed concern is that millennials are too burdened with student debts and poor job prospects to make it on their own. According to the narrative of generational dependency, the resurgence in multigenerational living is a trend hardly worth celebrating.
Or is it? Yes, many young college graduates have faced tough economic circumstances in recent years. But the trend toward embracing the multigenerational home began well before the Great Recession, suggesting something else is at work. A record 57 million Americans, or 18.1 percent of the population, lived in a multigenerational household in 2012, according to a Pew Research report, “In Post-Recession Era, Young Adults Drive Continuing Rise in Multi-Generational Living,” released on June 17, 2014. (You can include the First Family among the multigenerational households.) That’s up from 28 million, or 12.1 percent of the population, in 1980. Equally impressive, the return of the multigenerational household marks a striking reversal of the post-World War II decline. In 1940, 24.7 percent of the population resided in a multigenerational home, a living arrangement that bottomed in the early 1980s.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Farrell, Bloomberg
Torrey Pines Court Receives Funding for Renovation
August 06, 2014 —
Beverley BevenFlorez-CDJ STAFFSan Diego Source reported that “CIT Real Estate Finance provided…$60 million…to refinance existing debt and fund the renovations at Torrey Pines Court,” a five-building Class A office campus located in La Jolla, California. The 206,128 square foot complex, which resides on 9.24 acres, is adjacent to the Torrey Pines Golf Course. CIT has funded the project in partnership with Rockwood Capital and The Muller Company.
"We are excited to begin renovations that will complete our repositioning of Torrey Pines Court with state-of-the-art office space and amenities,” David Streicher, Partner at Rockwood Capital, stated according to a press release in the Wall Street Journal. “We expect that the renovations, coupled with the project's picturesque setting, will solidify Torrey Pines Court's position as the preferred office destination in the submarket. We thank CIT for working with us to create a sound financing package that will take this project to the next level."
Read the full story, San Diego Source...
Read the full story, Wall Street Journal... Read the court decisionRead the full story...Reprinted courtesy of
Insurance Policies Broadly Defining “Suits” May Prompt an Insurer’s Duty to Defend and Indemnify During the Chapter 558 Pre-Suit Notice Process
May 30, 2018 —
Daniel Garcia - Gordon & Rees Construction Law BlogIn Altman Contractors, Inc. v. Crum & Forster Specialty Insurance Company, No. SC16-1420, 2017 WL 6379535 (Fla. Dec. 14, 2017), the Florida Supreme Court addressed whether the notice and repair process set forth in chapter 558, Florida Statutes, constitutes a “suit” within the meaning of a commercial liability policy issued by Crum & Forster Specialty Insurance Company (“C&F”) to Altman Contractors, Inc. (“Altman”). The Court found that because the chapter 558 pre-suit process is an “alternative dispute resolution proceeding” as included in the definition of “suit” in the policy by C&F to Altman, C&F had a duty to defend Altman during the chapter 558 process, prior to the filing of a formal lawsuit.
Chapter 558, titled “Construction Defects,” sets forth procedural requirements before a claimant may file a construction defect action. It requires a claimant to serve a written notice of claim on the applicable contractor, subcontractor, supplier, and/or design professional prior to filing a construction defect lawsuit. The legislature intended for Chapter 558 to be an alternative dispute resolution mechanism in certain construction defect matters allowing an opportunity to resolve the claim without further legal process.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Garcia, Gordon & Rees Scully MansukhaniMr. Garcia may be contacted at
daniel.garcia@grsm.com
Rams Owner Stan Kroenke Debuts His $5.5 Billion Dream Stadium
September 14, 2020 —
Christopher Palmeri - BloombergThe first thing you notice that’s different about SoFi Stadium is that you can walk from the parking lot almost directly into the fifth level of the arena.
There’s no passing through gate after gate or ascending endless circular walkways. Construction workers dug up over 7 million cubic yards of dirt to build an arena that sits 100 feet (30 meters) below grade.
It’s one of the many features that make SoFi, the National Football League’s biggest stadium, surprisingly visitor-friendly. Not that fans will be able to experience it just yet. When the stadium debuts Sunday with the first game of the Los Angeles Rams’ season, it will be spectator-free -- the result of pandemic-spurred restrictions on gatherings. But it will still be a spectacle.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Palmeri, Bloomberg
Contract Should Have Clear and Definite Terms to Avoid a Patent Ambiguity
December 11, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf you need more of a reason to have contracts with clear and definite terms, this case is it. This case exemplifies what can happen if the contract, not only does not have clear and definite terms, but contains a patent ambiguity. The contract will be deemed unenforceable which will make one of the contracting parties very unhappy!
In Bowein v. Sherman, 48 Fla.L.Weekly D2208a (Fla. 6th DCA 2023), the buyer and seller entered into a real estate transaction. The transaction was for $2 Million. The purchase-and-sale agreement included the address and legal description of a parcel to be sold. However, there was a section in the agreement called “Other Terms and Conditions” which identified that the offer was actually for four properties that were being sold by the seller. When it came to closing time, the seller refused to close because the seller disputed that the $2 Million purchase price was for all four of his properties. The buyer sued the seller for specific performance to force the sale which the trial court agreed in favor of the buyer. However, the appellate court did not.
First, the appellate court held that “[t]he equitable remedy of specific performance may be granted only where the parties have actually entered into a definite and certain agreement.” Bowein, supra (quotation and citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Give Way or Yield? The Jurisdiction of Your Contract Does Matter! (Law note)
March 05, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaHave you ever been to England? If so, you’ve likely seen their version of our “Yield” sign– the “Give Way” sign. It is a bit jarring to those from this side of the “big pond”.
Similarly, contracts can be worded differently– and, interpreted differently– depending on the state that you are in. This is why it is always a good idea to have your contract or proposal vetted for the state(s) where you provide professional services.
When confronted with a “give way” sign you have the general idea of yielding, but might be confused by that whole “left side of the road” thing in some countries, where if you are turning right, you must give way to all vehicles coming towards you including those turning left. Likewise, you might have a good understanding of your construction contract in one state, but not how it would be interpreted in another state.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Newmeyer & Dillion Partner Aaron Lovaas & Casey Quinn Recognized by Super Lawyers
July 21, 2018 —
Newmeyer & DillionLAS VEGAS, Nev. – JUNE 11, 2018 – Prominent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that partner
Aaron Lovaas has been selected to the 2018 Mountain States Super Lawyers list, and associate
Casey Quinn has been selected to the 2018 Mountain States Rising Stars list by Super Lawyers. Each year, no more than 5 percent of lawyers are named to a Super Lawyers list and less than 2.5 percent are named to the Rising Stars list. This is the 9th consecutive year Lovaas has been honored, while Quinn has been consistently selected as a Rising Star honoree in prior years.
Aaron Lovaas is a partner in the Las Vegas office. As a transactional attorney and business litigator, Lovaas has the ability to evaluate legal issues from both points of view and help his clients understand their best option. He also brings to the table experience as a business owner, having owned and managed his own boutique law firm for 12 years.
Casey Quinn, an associate in the Las Vegas office, focuses his practice in complex commercial and construction litigation. He represents a variety of business entities in commercial disputes, including contract claims, business torts, privacy lawsuits, defamation, and fraud. Quinn is a past chair of the Construction Law section of the State Bar of Nevada and has successfully argued before the Supreme Court of Nevada, as well as settled disputes through various forms of conflict resolution including mediation and arbitration.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high-degree of peer recognition and professional achievement. The patented selection process includes independent research, peer nominations and peer evaluations.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of