Excess Carrier Successfully Appeals Primary Insurer’s Summary Judgment Award
December 09, 2011 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the excess carrier was given inadequate notice of the underlying arbitration, the trial court determined it shared responsibility with the primary carrier for the arbitration award. Finding disputed issues of fact, the Washington Court of Appeals reversed in Am. States Ins. Co. v. Century Surety Co., 2011 Wash. App. LEXIS 2488 (Wash. Ct. App. Oct. 31, 2011).
The primary insurer, American States, issued two liability policies to Professional Home Builders (PHB), a siding contractor. The policies were for successive years, 1998-1999 and 1999-2000. Each policy had annual limits of $1 million per occurrence. PHB also had a commercial excess liability policy for 1999-2000 with Century Surety Company.
PHB was sued by Residential Investment Partners (RIP) for construction defects after moisture entered the building envelope, causing decay and damage. Century’s expert determined the decay started before the 1999-2000 policy period.
RIP and PHB went to arbitration.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Chamber of Commerce CEO Calls for Change to Condo Defect Law
March 05, 2015 —
Beverley BevenFlorez - CDJ STAFFAccording to the Denver Business Journal, Dennis Houston, president and CEO of the Parker Chamber of Commerce in Colorado, spoke at the state’s capitol recently, calling legislators “to make it harder for attorneys to file class-action lawsuits against condominium builders so that areas like his can attract a workforce of millennials.” Houston and other Chamber of Commerce leaders gathered at the capitol “to lobby for sensible energy policies and construction defects reform, among other things.”
Read the court decisionRead the full story...Reprinted courtesy of
The “Climate 21 Project” Prepared for the New Administration
December 21, 2020 —
Anthony B. Cavender - Gravel2GavelThis is a brief review of the recently released “Climate 21 Project” policy memo. It is the work of many former members of the Obama Administration who are deeply concerned about climate change and what steps the new administration can take in the first 100 days to confront a problem. Offering “actionable advice” rather than a policy agenda, the group recognizes that Congress must do its part by providing new statutory authorities within the early days of the new administration, and the President must be prepared to aggressively exercise the powers of his office. As the members of the Group see it, there are four interlocking crises facing the President: (a) the COVID-19 pandemic; (b) the economic devastation visited upon many people by the pandemic; (c) racial injustice; and (d) accelerating threats posed by climate change.
Accordingly:
1. The Executive Office of the President must take stronger steps to reduce greenhouse gas emissions through domestic investment, rulemakings, policy changes, and international diplomacy. A new Special Assistant for Climate Change must be created to take charge of these climate change initiatives. There should also be established in the Executive Office of the President a National Climate Change Council. All agencies must be advised of the urgency of this problem. The paper seems to envision a substantial growth in the White Hose staff.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
A Homeowner’s Subsequent Action is Barred as a Matter of Law by way of a Prior “Right to Repair Act” Claim Resolved by Cash Settlement for Waiver of all Known or Unknown Claims
February 26, 2015 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinDavid Belasco v. Gary Loren Wells et al. (2015) B254525
OVERVIEW
In a decision published on February 17, 2015, the Second District Court of Appeal made clear that settlement agreements containing waivers of unknown claims in connection with a construction of a property, absent fraud or misrepresentation, will be upheld. In brief, the homeowner plaintiff had made a claim against the builder pursuant to California Code of Civil Procedure Section 896 (“Right to Repair”) and settled for a cash payment and obtained a Release of all Claims including for all known and unknown claims. The court held that homeowner’s subsequent construction defect claim was barred pursuant to the terms and conditions of the earlier release.
DISCUSSION
Plaintiff and Appellant, David Belasco ("Belasco"), purchased a newly construction home in Manhattan Beach from builder Gary Loren Wells ("Wells"). Two years after purchasing the property, Belasco filed a Complaint for construction defects, which eventually resulted in settlement between the parties. The settlement agreement included a California Civil Code Section 1524 waiver of all known or unknown claims with the word "claims" defined in part as “any and all known and unknown construction defects." Six years later in 2012, Belasco filed a Complaint alleging a claim, amongst others, that the defective and leaky roof breached the statutory warranty on new construction under California Civil Code section 896 ("Right to Repair Act").
Relying on San Diego Hospice v. County of San Diego (1995) 31 Cal.App.4th 1048, Wells and Wells' surety, American Contractors Indemnity Company (collectively "Wells"), filed a motion for summary judgment contending that the 2012 action was barred by the settlement of Belasco’s prior Complaint against Wells for construction defects to his home. When the trial court ruled in favor of Wells, Belasco appealed. Belasco, a patent attorney, made the following contentions:(1) the general release and section 1542 wavier in the settlement agreement for patent construction defects is not a "reasonable release" of a subsequent claim for latent construction defects within the meaning of section 929 and the “Right to Repair” Act; (2) a reasonable release can only apply to a "particular violation" and not to a latest defect under the language of section945.5, subdivision (f), and the settlement was too vague to be valid because it does not reference a "particular violation;" (3) section 932 of the California Civil Code specifically authorizes an action on "[s]subsequently discovered claims of unmet standards;" (4) public policy prohibits use of a general release and section 1542 waiver to bar a subsequent claim for latent residential construction defects; and (5) a genuine issue of material fact exists concerning Belasco's fraud and negligence claims that would have voided the settlement pursuant to section 1668.
Pursuant to the "Right to Repair Act" Section 929 subsection (a), a builder can make a cash offer in lieu of a repair and the homeowner is free to accept or reject such offer. Section 929subsection (b) goes on to state that
"[t]he builder may obtain a reasonable release in exchange for the cash payment. The builder may negotiate the terms and conditions of any reasonable release in terms of scope and consideration in conjunction with a cash payment under this chapter."
The Second District Court of Appeal ruled that the prior cash settlement, with a release and section 1524 wavier, was a "reasonable release" under the language of California Civil Code Section 929.
On multiple occasions, the Court noted that Belasco is an attorney and was represented by an attorney during the negotiation of the settlement agreement. By executing the agreement with express language regarding what claims were to be release, Belasco released Wells of "any and all claims" due to "any and all known and unknown construction defects." The Court reasoned that because Belasco is an attorney in his own right, he should have understood the import of the Section 1542 waiver and had the opportunity to reject or revise the settlement agreement prior to binding himself to it. The Court further found that the agreement "could not have been more clear" regarding the waiver of all unknown and known construction defect claims and therefore was not vague. Belasco's additional contentions were found to be without merit because Belasco availed himself of the statutory remedy of a cash settlement in lieu of repairs and voluntarily entered into a negotiated settlement agreement. Lastly, Belasco failed to present any evidence regarding his misrepresentation claim.
When a homeowner files a "Right to Repair Act" claim, often it seems that only two options exist: either repair the alleged defects or go to court. However, Belasco is a reminder to builders that the "Right to Repair Act" does offer an avenue for settlement. The Second District Court of Appeal presented a clear, unqualified opinion regarding the validity and enforceability of settlement agreements releasing all known or unknown construction defects in a single family home case. The Court will hold parties to the settlements they agree to. This is especially so when one of the parties is an attorney and provides deposition testimony expressly acknowledging that he understood the scope of the agreement. Attorneys for builders should always include a waiver of all known and unknown claims, which pursuant to Belasco and San Diego Hospice, will ensure that any future claims at the property will be effectively barred by the terms of the settlement agreement.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Is Privity of Contract with the Owner a Requirement of a Valid Mechanic’s Lien? Not for GC’s
January 04, 2021 —
Christopher G. Hill - Construction Law MusingsAs any reader of this construction law blog knows, mechanic’s liens make up much of the discussion here at Construction Law Musings. A recent case out of Fairfax County, Virginia examined the question of whether contractual privity between the general contractor and owner of the property at issue is necessary. As a reminder, in most situations, for a contract claim to be made, the claimant has to have a direct contract (privity) with the entity it sues. Further, for a subcontractor to have a valid mechanic’s lien it would have to have privity with the general contractor or with the Owner.
The Fairfax case, The Barber of Seville, Inc. v. Bironco, Inc., examined the question of whether contractual privity is necessary between the general contractor and the Owner. In Bironco, the claimant, Bironco, performed certain improvements for a barbershop pursuant to a contract executed by the two owners of the Plaintiff. We wouldn’t have the case here at Musings if Bironco had been paid in full. Bironco then recorded a lien against the leasehold interest of The Barber of Seville, Inc., the entity holding the lease. The Plaintiff filed an action seeking to have the lien declared invalid because Brionco had privity of contract with the individuals that executed the contract, but not directly with the corporate entity.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Defect Claim over LAX Runways
October 22, 2013 —
CDJ STAFFThe city of Los Angeles is claiming that problems with the south runway at Los Angeles International Airport are due to construction defects. The city as filed a lawsuit against four of the firms involved in building the runway, CH2M Hill, R&L Brosamer, HNTB, and Tutor-Saliba Corp. The lawsuit also includes the possibility of naming up to 200 individuals or corporations.
The suit alleges that the firms incorrectly installed the concrete, leading to accelerated wear. As a result, renovation of the runway will likely have to be done earlier than anticipated. The runway was opened in 2007 as part of a safety improvement effort.
Read the court decisionRead the full story...Reprinted courtesy of
New World Cup Stadiums Failed at their First Trial
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFProblems abounded at the inaugural match at one of the new World Cup stadiums in Manaus, Brazil, reported The News Tribune. Problems also were reported at the Arena da Amazonia. Bathrooms weren’t completed, roofs leaked, and some fans were sold tickets for seats that didn’t exist. Furthermore “construction material could be seen in some places and many wheelchair fans had difficulties accessing their seats.”
"This is a critical point that needs to be reevaluated, it can't happen again," said Miguel Capobiango, one of the officials in charge of World Cup preparations in Manaus, as quoted by The News Tribune. "But this is why we have these test events."
Read the court decisionRead the full story...Reprinted courtesy of
Federal District Court Dismisses Property Claim After Insured Allows Loss Location to Be Destroyed Prior to Inspection
September 29, 2021 —
James M. Eastham - Traub LiebermanIn BMJ Partners LLC v. Arch Specialty Insurance Co., No. 20-CV-03870, 2021 WL 3709182 (N.D. Ill. Aug. 20, 2021), the United States District Court for the Northern District of Illinois dismissed, with prejudice, a coverage action filed by an insured based on a failure to comply with a request to inspect the involved property under Rule 34 of the Federal Rules of Civil Procedure. The loss at issue involved a hail-damaged building in Carpentersville, Illinois. During the discovery phase of the litigation, the property insurer served a request to inspect the subject property under FRCP Rule 34. After ignoring numerous requests to schedule the inspection, the insurer filed a motion to dismiss for failure to prosecute or, alternatively, to compel an inspection. After the motion was filed, a status hearing was conducted where the insured’s counsel advised the Court of his intention to file a motion to withdraw from representation of the insured. After the date set to file the motion to withdraw passed without anything being filed, the Court entered an order directing the insured to show cause why the matter should not be dismissed for lack of prosecution.
In response to the order to show cause, the insured advised the Court that instead of responding to the property insurer’s discovery requests, the insured sold the property to a buyer who subsequently tore down the building. In light of what the Court described as the insured’s “flabbergasting admission”, the Court was compelled to grant the motion to dismiss and do so with prejudice. In support of the “extreme sanction” of dismissing the matter with prejudice, the Court first noted that the insured had not come close to justifying a discharge of the pending show-cause order. Rather, the insured’s responsive filing refers to the Court's show cause order only indirectly and does not deny, or offer any justification for, disregarding case-related communications for several months. Even if that were not enough, the Court further held that the insured’s spoliation of evidence likewise provides sufficient basis for dismissal given that Courts have inherent authority to sanction parties for failure to preserve potential evidence. According to the Court, dismissal with prejudice was the only appropriate sanction in light of the insured’s violation of the obligation to preserve the property. Not only did the insured ignore multiple requests from the insurer to inspect, but during the same time frame the insured found time to allow inspections of the building as part of the sale by both the Village of Carpentersville and the property's buyer.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com