Contractual Indemnification Limitation on Florida Public Projects
July 28, 2016 —
David Adelstein – Florida Construction Legal UpdatesConstruction contract indemnification provisions are governed under Florida Statute s. 725.06. This is a very important statute to know if you are drafting indemnification provisions for any type of construction contract. (There is also Florida Statute s. 725.08 that discusses indemnification provisions applicable to design professionals that is also worth knowing.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
After 15 Years, Settlement Arrested at San Francisco's Millennium Tower
June 26, 2023 —
Nadine M. Post - Engineering News-RecordAfter overcoming several snags, the team for the voluntary effort to stem future significant settlement and tilting at San Francisco’s 645-ft-tall Millennium Tower has declared the project a success, now that loads have been fully transferred to 18 new perimeter piles driven to bedrock.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Tall and Sustainable Is Not an Easy Fix
June 01, 2020 —
Christopher G. Hill - Construction Law MusingsWay back in 2009, I discussed the interaction between taller and taller buildings and sustainable (“green”) building. Back then, the reference was to the construction of skyscrapers in the Middle East and Europe. The initially referenced ENR article was written in the context of an urban retrofit of some of Chicago’s taller buildings to make them more sustainable.
Just this week, ENR published another article relating to sustainability and super tall buildings. The gist of the article is that while many see taller (rather than wider) as the trend to meld an urban population explosion with more sustainable building practices, this goal is not an easy one to meet.
For one, according to the article, energy performance metrics are hard to obtain, both due to the relative newness of these buildings and the seeming reluctance of certain owners to provide the data. Bob Pratt, a managing director in the Shanghai office of developer Tishman Speyer Properties, is quoted in the article, stating
Once we have measuring sticks about performance, we will know what to do” to make buildings sustainable.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrissghill@constructionlawva.com
What Happens When a Secured Creditor Files a Late Claim in an Equity Receivership?
September 28, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogPitting a receivership court’s inherent equitable powers against pre-existing property rights can lead to some pretty interesting questions. In SEC v. Wells Fargo Bank, N.A., 848 F.3d 1339, 1343-44 (11th Cir. 2017), the Eleventh Circuit recently examined whether a district court’s inherent authority to establish a claims submission process allowed the court to extinguish a security interest in real property based solely upon an untimely proof of claim. Much to the relief of secured creditors, the Eleventh Circuit held that the district court erred, as a matter of law, by extinguishing the creditor’s pre-existing property rights under those circumstances.
Introduction
Equity vests a district court with “‘broad powers and wide discretion to determine relief in an equity receivership.’” Wells Fargo, 848 F.3d at 1343-44 (quoting SEC v. Elliot, 953 F.2d 1560, 1566 (11th Cir. 1992)). These powers include: (i) establishing procedures for the submission of claims to a receiver, and (ii) setting a claims bar date. Id. at 1344 (citing SEC v. Tipco, Inc., 554 F.2d 710, 711 (5th Cir. 1977)).
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Contract Provisions That Help Manage Risk on Long-Term Projects
June 29, 2020 —
Jason Lambert - Construction ExecutiveFew things can dampen the thrill and promise of a newly closed construction deal than the realization that it could quickly become a losing proposition for the contractor depending on economic and other conditions. In an era of instant information, constantly adjusting markets and political extremes, projects that start under one set of assumptions or conditions can occur or conclude under much different ones. While no one has a crystal ball, there are contractual provisions that can provide clear guidance in the face of many “what ifs” that can arise in construction.
One of the chief concerns a contractor should have in a project lasting more than a few months is what impact price increases will have on the profitability of the job. On a true cost-plus project, this may be of little concern, but on any project with a limitation on costs or a guaranteed maximum price, contractors should insist on a procedure to revisit the limitation or price if certain conditions change.
This can be as simple as allowing the contractor to receive an upward adjustment in the price if costs increase by more than a certain percentage. It can be as complicated as requiring multiple new bids and disclosures to the property owner, architect or project manager and allowing approval of new suppliers or subcontractors to limit cost increases to the cheapest increase. The protection—and certainty—to the contractor though, comes from having a process in the contract to address cost increases, whether it is simple or complex.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lambert may be contacted at
Jason.lambert@dinsmore.com
Georgia Court of Appeals Holds That Insurer Must Defend Oil Company Against Entire Lawsuit
October 07, 2019 —
Lawrence J. Bracken II, Michael S. Levine & Alexander D. Russo - Hunton Andrews KurthThe Georgia Court of Appeals recently affirmed a grant of summary judgment in favor of Mountain Express Oil Company on its breach of contract claim against liability insurer, Southern Trust Insurance Company. Empire Petroleum brought claims against Mountain Express for breach of contract, injunctive relief, and libel or slander, among others. Mountain Express sought a defense to that lawsuit under its insurance policy with Southern Trust. Southern Trust contended that the insurance policy did not cover Empire’s non-libel/slander claims, and therefore reimbursed Mountain Express for only a portion of its attorneys’ fees. After the Empire lawsuit settled, Mountain Express sued Southern Trust for breach of contract and bad faith for failing to pay the remaining defense costs, contending that Southern Trust had a duty to defend the entire lawsuit.
The Georgia Court of Appeals affirmed the trial court’s grant of summary judgment to Mountain Express on its breach of contract claim. Citing policy language stating that “[the insurer] will have the right and duty to defend the insured against any ‘suit’ seeking those damages,” the court held that Southern Trust was obligated to defend the entire lawsuit. Specifically, in reaching that conclusion, the court noted that by agreeing to defend any “suit,” not any “claim,” Southern Trust obligated itself to defend the entire lawsuit if any claim could be covered under the policy. Accordingly, Southern Trust breached the policy when it only agreed to defend some of the claims against its insured.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Montana Trial Court Holds That Youths Have Standing to Bring Constitutional Claims Against State Government For Alleged Climate Change-Related Harms
September 18, 2023 —
Paul A. Briganti & Julia Castanzo - White and Williams LLPOn August 14, 2023, in a “landmark” ruling, a Montana state court held that youth plaintiffs had standing to assert constitutional claims against the State of Montana, its governor and state agencies for “ignoring” the impact of greenhouse gas (GHG) emissions on climate change. Held v. State of Montana, Cause No. CDV-020-307 (1st Judicial Dist. Ct., Lewis & Clark Cty., Mt.). Agreeing with the plaintiffs, the court concluded that a limitation in the Montana Environmental Policy Act (MEPA), which prohibited the state from considering climate impacts when issuing permits for energy projects, violated the plaintiffs’ right under the state constitution to a “clean and healthful environment.”
MEPA, enacted in 1971, states that its purposes include “provid[ing] for the adequate review of state actions in order to ensure that . . . environmental attributes are fully considered by the legislature in enacting laws to fulfill constitutional obligations . . . .” In 2011, the legislature amended the statute to curtail the scope of environmental reviews. Under the so-called MEPA limitation, Montana agencies cannot consider “an evaluation of greenhouse gas emissions and corresponding impacts to the climate in the state or beyond the state’s borders.” Mont. Code Ann. § 75-1-201(2)(a). In 2023, the legislature added a provision that eliminated equitable remedies (i.e., the ability to “vacate, void, or delay a lease, permit, license, certificate, authorization, or other entitlement or authority”) for litigants who “claim that [an] environmental review is inadequate based in whole or in part upon greenhouse gas emissions and impacts to the climate in Montana or beyond Montana’s borders . . . .” Id. § 75-1-201(6)(a)(ii).
Reprinted courtesy of
Paul A. Briganti, White and Williams LLP and
Julia Castanzo, White and Williams LLP
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Ms. Castanzo may be contacted at castanzoj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court Rejects “Wholly Groundless” Exception to Question of Arbitrability
February 06, 2019 —
Justin Fortescue - White and Williams LLPIn newly appointed Supreme Court Justice Brett Kavanaugh’s first opinion, the United States Supreme Court held that the “wholly groundless” exception to arbitrability, which some federal courts had relied on as justification to decide questions of arbitrability over the express terms of a contract, was inconsistent with the Federal Arbitration Act and Supreme Court precedent. Based on this decision, where a contract delegates the question of arbitrability to an arbitrator, courts must respect the parties’ contract and refer the question to the arbitrator. Schein v. Archer & White, 586 U.S. __ (2019).
In Schein, Archer & White brought a lawsuit against Henry Schein alleging violations of federal and state antitrust laws and seeking both monetary damages and injunctive relief. The relevant contract between the parties contained an arbitration provision that provided:
“Any dispute arising under or related to this Agreement (except for actions seeking injunctive relief . . .) shall be resolved by binding arbitration in accordance with the arbitration rules of the American Arbitration Association.”
Read the court decisionRead the full story...Reprinted courtesy of
Justin Fortescue, White and Williams LLPMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com