Limiting Liability: Three Clauses to Consider in your Next Construction Contract
June 25, 2019 —
Tara Lynch - Gordon & Rees Construction Law BlogIn your next contract, consider including some (or all!) of the following clauses to limit your liability and maximize your profits.
Waiver of Consequential Damages
While a proven breach of contract will leave a design professional or contractor exposed to direct or compensatory damages, a waiver of consequential damages will help “stop the bleeding” and protect the design professional or contractor from paying every damage that might flow from the breach. Consequential damages include those damages which indirectly flow from the breach of contract, for example, lost rents, lost profits, lost use, lost opportunity, loss of employee productivity, and damages to reputation.
The American Institute of Architects (AIA) has included a mutual waiver of consequential damages in its sample A201 for over 20 years. The AIA provision includes a definition of consequential damages which are waived, including many of the examples cited above. However, the AIA waiver of consequential damages clause carves out an exception for liquidated damages to the owner. Prudent design professionals and contractors will strike this exception so as not to render the clause meaningless. A well-drafted waiver clause will be mutual, will define which damages are consequential versus direct, and will not contain exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
Tara Lynch - Gordon & Rees Scully MansukhaniMs. Lynch may be contacted at
tlynch@grsm.com
When Coronavirus Cases Spike at Construction Jobsites
July 27, 2020 —
Richard Korman, Scott Judy & Jeff Rubenstone - Engineering News-RecordWhen Covid-19 took hold in several US states in early spring, Choate Construction responded, as many contractors did, by quickly adopting federal workplace safety guidelines for disinfecting surfaces and maintaining social distancing. Enhanced by various state lockdown measures for businesses and the general public, the new safety system seemed to work with only a handful of workers on Choate’s projects testing positive.
Reprinted courtesy of Engineering News-Record reporters
Richard Korman,
Scott Judy and
Jeff Rubenstone
Mr. Korman may be contacted at kormanr@enr.com
Mr. Judy may be contacted at judys@enr.com
Mr. Rubenstone may be contacted at rubenstonej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 —
Shaun McParland BaldwinThe Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Read the court decisionRead the full story...Reprinted courtesy of
A Homeowner’s Subsequent Action is Barred as a Matter of Law by way of a Prior “Right to Repair Act” Claim Resolved by Cash Settlement for Waiver of all Known or Unknown Claims
February 26, 2015 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinDavid Belasco v. Gary Loren Wells et al. (2015) B254525
OVERVIEW
In a decision published on February 17, 2015, the Second District Court of Appeal made clear that settlement agreements containing waivers of unknown claims in connection with a construction of a property, absent fraud or misrepresentation, will be upheld. In brief, the homeowner plaintiff had made a claim against the builder pursuant to California Code of Civil Procedure Section 896 (“Right to Repair”) and settled for a cash payment and obtained a Release of all Claims including for all known and unknown claims. The court held that homeowner’s subsequent construction defect claim was barred pursuant to the terms and conditions of the earlier release.
DISCUSSION
Plaintiff and Appellant, David Belasco ("Belasco"), purchased a newly construction home in Manhattan Beach from builder Gary Loren Wells ("Wells"). Two years after purchasing the property, Belasco filed a Complaint for construction defects, which eventually resulted in settlement between the parties. The settlement agreement included a California Civil Code Section 1524 waiver of all known or unknown claims with the word "claims" defined in part as “any and all known and unknown construction defects." Six years later in 2012, Belasco filed a Complaint alleging a claim, amongst others, that the defective and leaky roof breached the statutory warranty on new construction under California Civil Code section 896 ("Right to Repair Act").
Relying on San Diego Hospice v. County of San Diego (1995) 31 Cal.App.4th 1048, Wells and Wells' surety, American Contractors Indemnity Company (collectively "Wells"), filed a motion for summary judgment contending that the 2012 action was barred by the settlement of Belasco’s prior Complaint against Wells for construction defects to his home. When the trial court ruled in favor of Wells, Belasco appealed. Belasco, a patent attorney, made the following contentions:(1) the general release and section 1542 wavier in the settlement agreement for patent construction defects is not a "reasonable release" of a subsequent claim for latent construction defects within the meaning of section 929 and the “Right to Repair” Act; (2) a reasonable release can only apply to a "particular violation" and not to a latest defect under the language of section945.5, subdivision (f), and the settlement was too vague to be valid because it does not reference a "particular violation;" (3) section 932 of the California Civil Code specifically authorizes an action on "[s]subsequently discovered claims of unmet standards;" (4) public policy prohibits use of a general release and section 1542 waiver to bar a subsequent claim for latent residential construction defects; and (5) a genuine issue of material fact exists concerning Belasco's fraud and negligence claims that would have voided the settlement pursuant to section 1668.
Pursuant to the "Right to Repair Act" Section 929 subsection (a), a builder can make a cash offer in lieu of a repair and the homeowner is free to accept or reject such offer. Section 929subsection (b) goes on to state that
"[t]he builder may obtain a reasonable release in exchange for the cash payment. The builder may negotiate the terms and conditions of any reasonable release in terms of scope and consideration in conjunction with a cash payment under this chapter."
The Second District Court of Appeal ruled that the prior cash settlement, with a release and section 1524 wavier, was a "reasonable release" under the language of California Civil Code Section 929.
On multiple occasions, the Court noted that Belasco is an attorney and was represented by an attorney during the negotiation of the settlement agreement. By executing the agreement with express language regarding what claims were to be release, Belasco released Wells of "any and all claims" due to "any and all known and unknown construction defects." The Court reasoned that because Belasco is an attorney in his own right, he should have understood the import of the Section 1542 waiver and had the opportunity to reject or revise the settlement agreement prior to binding himself to it. The Court further found that the agreement "could not have been more clear" regarding the waiver of all unknown and known construction defect claims and therefore was not vague. Belasco's additional contentions were found to be without merit because Belasco availed himself of the statutory remedy of a cash settlement in lieu of repairs and voluntarily entered into a negotiated settlement agreement. Lastly, Belasco failed to present any evidence regarding his misrepresentation claim.
When a homeowner files a "Right to Repair Act" claim, often it seems that only two options exist: either repair the alleged defects or go to court. However, Belasco is a reminder to builders that the "Right to Repair Act" does offer an avenue for settlement. The Second District Court of Appeal presented a clear, unqualified opinion regarding the validity and enforceability of settlement agreements releasing all known or unknown construction defects in a single family home case. The Court will hold parties to the settlements they agree to. This is especially so when one of the parties is an attorney and provides deposition testimony expressly acknowledging that he understood the scope of the agreement. Attorneys for builders should always include a waiver of all known and unknown claims, which pursuant to Belasco and San Diego Hospice, will ensure that any future claims at the property will be effectively barred by the terms of the settlement agreement.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
When a Construction Lender Steps into the Shoes of the Developer, the Door is Open for Claims by the General Contractor
February 18, 2015 —
Kevin Brodehl – California Construction Law BlogThank you to my partner Garret Murai for giving me the opportunity to post again on his excellent California Construction Law Blog. I am the author/editor of the Money and Dirt Blog, where I focus on issues relating to real estate investment, development, and secured lending.
On the
Money and Dirt Blog, I recently posted an
article on an interesting new secured lending opinion from the California Court of Appeal (Fourth District in Riverside), California Bank & Trust v. Del Ponti. That blog post focused on guaranty liability, and the court’s holding that there are limits to the defenses that a guarantor can lawfully waive.
But that same decision also highlights valuable lessons regarding the relationship between construction lenders and general contractors in distressed projects, which I’ll cover here. In short, the court held that when a construction lender “steps into the shoes” of the developer to manage a distressed project, the lender might open the door to liability to the general contractor under theories of breach of contract and promissory estoppel.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin Brodehl, Wendel Rosen Black & Dean LLPMr. Bordehl may be contacted at
kbrodehl@wendel.com
London's Walkie Talkie Tower Voted Britain's Worst New Building
September 03, 2015 —
Neil Callanan – BloombergThe skyscraper at 20 Fenchurch Street in the City of London, nicknamed the Walkie Talkie, is the worst new building in Britain, according to a panel assembled by Building Design magazine.
The 37-story tower, designed by Rafael Vinoly, was made famous two years ago when a beam of light reflected from the building melted parts of a Jaguar sports car. The problem has since been remedied by developers Land Securities Group Plc and Canary Wharf Group Plc.
It is a challenge finding anyone who has something positive to say about this building,” Thomas Lane, editor of the magazine for architects, said in a statement on Thursday. “Londoners now have to suffer views of this bloated carbuncle crashing into London’s historic skyline like an unwelcome guest at a party from miles away.”
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, Bloomberg
Toolbox Talk Series Recap – Best Practices for Productive Rule 26(f) Conferences on Discovery Plans
May 13, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the April 4, 2024 edition of Division 1’s Toolbox Talk Series,
Julian Ackert and
Steve Swart presented on how to prepare for and structure Rule 26(f) conferences to be more effective. While Swart and Ackert focused on the requirements of Federal Rule of Civil Procedure 26(f) regarding the requisite conference of the parties prior to a scheduling conference or scheduling order, it is worth noting that many states have substantially similar requirements.
Rule 26(f) requires the parties to (i) discuss the nature and basis of their claims or defense; (ii) make or arrange for mandatory disclosures pursuant to Rule 26(a)(1); (iii) discuss issues about preserving discoverable information (including Electronically Stored Information – “ESI”); and (iv) develop a proposed discovery plan. Swart and Ackert’s presentation focused on the preservation of ESI and the proposed discovery plan.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at
dmackin@cozen.com
Statute of Limitations Upheld in Construction Defect Case
September 30, 2011 —
CDJ STAFFThe Missouri Court of Appeals has ruled in Ball v. Friese Construction Co., finding that Mr. Ball’s claims were barred by the statute of limitations.
Mr. Ball hired Friese Construction Company to build a single-family home. The sale was completed on March 29, 2001. That December, Mr. Ball complained of cracks in the basement floor. SCI Engineering, n engineering firm, hired by Friese, determined that the home’s footing had settled and recommended that Mr. Ball hire a structural engineer to determine if the footings were properly designed and sized. In September 2002, the structural engineer, Strain Engineering, determined that the cracks were due to slab movement, caused in part by water beneath the slab, recommending measures to move water away from the foundation. In 2005, Mr. Ball sent Friese correspondence “detailing issues he was having with the home, including problems with the basement slab, chimney structure, drywall tape, and doors.” All of these were attributed to the foundation problems. In 2006, Friese stated that the slab movement was due to Ball’s failure to maintain the storm water drains.
In 2009, Ball received a report from GeoTest “stating the house was resting on highly plastic clay soils.” He sued Friese in May, 2010. Friese was granted a summary judgment dismissing the suit, as the Missouri has a five-year statute of limitations. Ball appealed on the grounds that the extent of the damage could not be determined until after the third expert report. The appeals court rejected this claim, noting that a reasonable person would have concluded that after the conclusion of SCI and Strain Engineering that “injury and substantial damages may have occurred.”
The court concluded that as there were not “continuing wrongs causing new and distinct damages,” he should have filed his lawsuit after the first two expert reports, not waiting seven years for a third expert to opine.
Read the court’s decision…