Inspired by Filipino Design, an Apartment Building Looks Homeward
May 22, 2023 —
Sarah Holder - BloombergAusterity and efficiency aren’t the first words that come to mind when you see the angled sawtooth bays of Tahanan Supportive Housing, or catch a glimpse of a rainbow through its lobby. But the dramatic exterior and joyful interior of this San Francisco building are both products of their constraints.
When David Baker Architects was approached to design the six-story development, the goal was aggressive: Produce 145 units of permanent supportive housing at under $400,000 a unit, and have the operation up and running in less than three years. The firm accepted the challenge, and by 2022, Tanahan was fully leased to residents, all of whom are San Franciscans who have struggled with chronic homelessness.
In a city where affordable units typically cost $600,000 to $700,000 each to construct, keeping in budget and meeting the deadline meant turning to the modular building company Factory OS. It also meant keeping variation at a minimum. The studios are identical, like Lego blocks; instead of being mirrored across a hallway, they’re just rotated 180 degrees. But nothing else about the building feels utilitarian.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Holder, Bloomberg
Insurance Measures Passed by 2015 Hawaii Legislature
June 10, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe 2015 Hawaii legislative session passed three insurance-related bills which have all been signed by the governor. Bills that have been enacted are the following:
SB0589 - We previously devoted this post to the legislation. The bill provides relief for residents in lava zones on the Big Island. The bill limits the number of property policies that an insurer can refuse to renew in a lava zone. Further, a moratorium on the issuance of policies can be lifted in a state of emergency due to the threat of imminent disaster from a lava flow.
SB0736 - Provisions relating to reimbursement for accident and health or sickness insurance benefits are amended. Further, the bill provides that prior to initiating any recoupment or offset demand efforts, an entity must send a written notice to the health care provider at least 30 days prior to engaging in recoupment or offset efforts. An entity may not initiate recoupment or offset efforts more than 18 months after the initial claim payment was received by the health care provider or health care entity.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indemnity Payment to Insured Satisfies SIR
March 11, 2014 —
Tred Eyerly – Insurance Law HawaiiIn response to certified questions from the Eleventh Circuit, the Florida Supreme Court found that a contractual indemnity payment to the insured satisfied the policy's SIR requirement. Intervest Constr. of Jax v. Gen. Fid. Ins. Co., 2014 Fl. LEXIS 568 (Fla. Feb. 6, 2014).
ICI Homes, Inc. a general contractor, hired Custom Cutting, Inc. to provide trim work, including installation of attic stairs in a residence ICI was building. Under the contract, Custom Cutting agreed to indemnify ICI for any damages resulting from Custom Cutting's negligence. The owner of the residence fell while using the attic stairs installed by Custom Cutting, injurying herself. The owner sued ICI, who sought indemnification from Custom Cutting.
ICI's policy with General Fidelity had a $1 million SIR. The policy also had a transfer of rights clause granting the insurer some subrogation rights.
The case was mediated. The parties agreed to a settlement of $1.6 million. Custom Cutting's insurer proposed paying $1 million to ICI to settle the indemnification claim. ICI, in turn, would pay that $1 million to the residence owner. A dispute arose over wither ICI or General Fidelity was responsible for paying the remaining $600,000.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Contractors Can No Longer Make Roof Repairs Following Their Own Inspections
July 02, 2018 —
Jason Feld & Alex Chazen - Kahana & Feld LLPCalifornia law mandates that any person who conducts roof inspections for a fee can no longer effectuate the actual repairs to the same property. Effective January 1, 2018, Business & Professions Code Section 7197 (Unfair Business Practices) deems it to be an unfair business practice for a home inspector who charges a homeowner a monetary fee for inspecting the property, to perform or offer to perform additional repairs due to the inherent financial interest and conflict raised by identifying alleged defects necessitating repairs. The new law is a result of California AB 1357, which was signed into law on October 5, 2017. The goal of the new law is to disincentivize a roof inspector from creating a report for the sole purpose of obtaining a bid to perform those documented repairs. The roof contractor can perform repairs identified in their report only after a twelve month “cooling period” which provides the homeowner an opportunity to obtain multiple bids/estimates for repairs based upon the inspector’s report. The new law also discourages home inspectors from providing a list of contractors who provide monetary referral fees back to the home inspector upon receiving repair work from the homeowner based exclusively on the home inspection report.
The California Business & Professions Code Section 7195(a)(1) defines a “home inspection” as a “non-invasive, physical examination, performed for a fee in connection with the transfer…of the real property…or essential components of the residential dwelling.” Home inspection includes “any consultation regarding the property that is represented to be a home inspection or any confusingly similar term.” Business & Professions Code section 7195(a)(2) further defines a “home inspection” as including energy efficiency and solar. A “home inspection report” is a written report prepared for a fee issued after an inspection. Business & Professions Code section 7195(c). It is noted that a home inspector does not have to be a licensed architect, professional engineer, or general contractor with a Class “B” license issued by the California Contractors State License Board, but “it is the duty of a home inspector who is not licensed as a general contractor, structural pest control operator, or architect, or registered as a professional engineer to conduct a home inspection with the degree of care that a reasonably prudent home inspector would exercise. Business & Professions Code section 7196.
Reprinted courtesy of
Jason Feld, Kahana & Feld LLP and
Alex Chazen, Kahana & Feld LLP
Mr. Feld may be contacted at jfeld@kahanalaw.com
Mr. Chazen may be contacted at achazen@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Pulls Phased Trigger On Its Statute of Repose
December 21, 2020 —
Kyle Rice - The Subrogation SpecialistIn D’Allesandro v. Lennar Hingham Holdings, LLC, 486 Mass 150, 2020 Mass. LEXIS 721, the Supreme Judicial Court of Massachusetts answered a certified question regarding how to apply the Massachusetts statute of repose, Mass. Gen. Laws ch. 260, § 2B, in regards to phased construction projects. The court held that, in this context, the completion of each individual “improvement” to its intended use, or the substantial completion of the individual building and the taking of possession for occupancy by the owner or owners, triggers the statute of repose with respect to the common areas and limited common areas of that building. Additionally, the court held that where a particular improvement is integral to, and intended to serve, multiple buildings (or the development as a whole), the statute of repose is triggered when the discrete improvement is substantially complete and open to its intended use.
In D’Allesandro, the action arose out of the construction, marketing, sale and management of the Hewitts Landing Condominium (the Condominium) project. Ultimately, 150 units were constructed over 24 phases of construction, enclosed in 28 different buildings. Throughout construction, the project’s architect submitted declarations to the Town of Hingham swearing that the individual units were “substantially complete” and could be occupied for their intended use. The Town of Hingham then issued certificates of occupancy for the unit or building.
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
Determining the Cause of the Loss from a Named Windstorm when there is Water Damage - New Jersey
March 23, 2020 —
Anna M. Perry - Saxe Doernberger & VitaWater damage, while one of the leading causes of loss under a property policy, often results in some of the most complex claims due to the intersection of exclusions, sublimits, and complex wording within the policy. One particularly difficult issue is whether water damage caused by a storm surge is covered by the flood sublimit, or under the general policy or water limit. In New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s (“NJTC v. Lloyd’s”), the New Jersey Appeals Court found that the “flood” sublimit of the policy should not apply as the cause of the loss was a “named windstorm” and not a “flood.”
In NJTC v Lloyd's the court was asked to determine whether a flood sublimit applied to losses sustained during Superstorm Sandy. The court found that although there was “flooding,” the water damage was more closely related to the “named windstorm”, and therefore, the $400 million policy limits should apply. The court focused its analysis on the definitions for “flood” and “named windstorm” and by applying the efficient proximate cause doctrine to determine which would apply.
When reviewing the definitions within the property policies, the court determined that although the loss would qualify under the definition of “flood,” the policy also contained a definition for “named windstorm” which “more specifically encompasses the wind driven water or storm surge associated with a ‘named windstorm’”1. In addition, the policy did not specifically state that “storm surge” associated with a “named windstorm” should be considered a “flood” event and fall under the “flood” sublimit.
Read the court decisionRead the full story...Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & VitaMs. Perry may be contacted at
amp@sdvlaw.com
Kumagai Drops Most in 4 Months on Building Defect: Tokyo Mover
June 11, 2014 —
Kathleen Chu and Kevin Buckland - BloombergKumagai Gumi Co. (1861), a Japanese construction company, fell the most in four months after saying an apartment complex it had built has defects.
The shares dropped 5.7 percent to 264 yen at the close of trading in Tokyo, the biggest decline since Feb. 4. Construction flaws in supporting pillars were found in the building completed in March 2003 in Yokohama City, south of Tokyo, the company said in a statement through the stock exchange today. The residents have been asked to relocate to temporary shelters and further investigation is required, it said.
“This is a big negative for Kumagai’s reputation and it may hurt the company’s future earnings,” said Yoji Otani, an analyst at Deutsche Bank AG in Tokyo.
The latest defect comes after Mitsubishi Estate Co. (8802) said in March it will rebuild a residential complex, constructed by Kajima Corp. (1812), in central Tokyo, after defects were found. Mitsui Fudosan Co. (8801) said it would repair some parts of an apartment building in Kawasaki City after the builder Shimizu Corp. (1803) found cracks in the concrete of some columns in April.
Ms. Chu may be contacted at kchu2@bloomberg.net; Mr. Buckland may be contacted at kbuckland1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen Chu and Kevin Buckland, Bloomberg
Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com