Colorado Finally Corrects Thirty-Year Old Flaw in Construction Defect Statute of Repose
March 29, 2017 —
Jesse Howard Witt - The Witt Law FirmThe Colorado Supreme Court has finally settled a decades-old conundrum surrounding the state’s construction defect statute of repose.
A statute of repose is similar to a statute of limitations insofar as both restrict the time a party can bring a claim. A statute of repose period begins on a fixed date (such as the day someone finishes work on a project), while a statute of limitations period begins when someone discovers an injury (such as a defectively installed window).
In 1986, at the height of the so-called “tort reform” movement, the Colorado General Assembly voted to shorten both the statute of repose and the statute of limitations for construction defect claims. Historically, Colorado’s statute of repose had given a homeowner ten years following construction to file an action, and its statute of limitations had required that any such action be filed within three years of the date that the claimant discovered a defect. After 1986, however, these time periods changed; the new statute of repose required suits to be filed within six years of the end of construction, and the new statute of limitations gave claimants only two years following discovery of the physical manifestation of a defect to seek legal relief.[1]
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Litigation at San Diego’s Alicante Condominiums?
March 25, 2011 —
Alicante HOA WebsiteAccording to recent posts in the Alicante HOA website, construction experts and legal counsel have been retained. The HOA board has been informed that testing of a variety of the building’s components are underway or will begin in the near future.
Read More...
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Court of Appeals Holds That Insurer Must Defend Oil Company Against Entire Lawsuit
October 07, 2019 —
Lawrence J. Bracken II, Michael S. Levine & Alexander D. Russo - Hunton Andrews KurthThe Georgia Court of Appeals recently affirmed a grant of summary judgment in favor of Mountain Express Oil Company on its breach of contract claim against liability insurer, Southern Trust Insurance Company. Empire Petroleum brought claims against Mountain Express for breach of contract, injunctive relief, and libel or slander, among others. Mountain Express sought a defense to that lawsuit under its insurance policy with Southern Trust. Southern Trust contended that the insurance policy did not cover Empire’s non-libel/slander claims, and therefore reimbursed Mountain Express for only a portion of its attorneys’ fees. After the Empire lawsuit settled, Mountain Express sued Southern Trust for breach of contract and bad faith for failing to pay the remaining defense costs, contending that Southern Trust had a duty to defend the entire lawsuit.
The Georgia Court of Appeals affirmed the trial court’s grant of summary judgment to Mountain Express on its breach of contract claim. Citing policy language stating that “[the insurer] will have the right and duty to defend the insured against any ‘suit’ seeking those damages,” the court held that Southern Trust was obligated to defend the entire lawsuit. Specifically, in reaching that conclusion, the court noted that by agreeing to defend any “suit,” not any “claim,” Southern Trust obligated itself to defend the entire lawsuit if any claim could be covered under the policy. Accordingly, Southern Trust breached the policy when it only agreed to defend some of the claims against its insured.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
The Road to Rio 2016: Zika, Super Bacteria, and Construction Delays. Sounds Like Everything is Going as Planned
July 28, 2016 —
Garret Murai – California Construction Law BlogAthletes began to arrive at the Olympic Village in Rio de Janeiro on Sunday in anticipation of the 2016 Summer Olympics which begin on August 5th.
Perhaps the most closely watched event, however, has already begun; and it has no medals. And that is whether Brazil can successfully pull off the Olympics at all.
For a city known for its Carnival the months leading up to the Olympics have been just as crazy and chaotic as the days leading up to Mardi Gras. There’s the Zika virus, the discovery of a “super” bacteria, the impeachment of its President, and Brazil’s worst recession in 100 years. And that’s just a partial list.
And then, of course, there’s the construction.
Cities bidding to host the Olympics often cite revenue from tourism and long-term capital improvements which will benefit its populace long after the games have ended as economic justification for hosting the Olympics. However, the cost to host the Olympics is often underestimated and Rio is no exception, running an estimated $6 billion over budget.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
UPDATE: Texas Federal Court Permanently Enjoins U.S. Department of Labor “Persuader Rule” Requiring Law Firms and Other Consultants to Disclose Work Performed for Employers on Union Organization Efforts
December 08, 2016 —
Aaron C. Schlesinger & Gregory R. Begg – Peckar & Abramson, P.C.As an update to our prior alert, on November 16, 2016, a federal judge in Texas issued a permanent injunction blocking the U.S. Department of Labor’s (“DOL”) “persuader rule” – a preliminary injunction had been granted this past June.
In rendering the permanent injunction, the court adopted the reasoning of its prior June 27, 2016 decision that granted a nationwide preliminary injunction on the rule. In the earlier decision, the court held that a temporary injunction was appropriate because the parties challenging the rule were likely to succeed on the merits of their claim […].
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. and
Gregory R. Begg, Peckar & Abramson, P.C.
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Mr. Begg may be contacted at gbegg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Washington Court Denies Subcontractor’s Claim Based on Contractual Change and Notice Provisions
January 29, 2024 —
Wendy Rosenstein - Ahlers Cressman & Sleight PLLCThe recent unpublished case, Cascade Civil Construction, LLC v. Jackson Dean Construction, Inc., et al.,[1] provides a legal justification for contractors to require a directive or change order in advance of performing changed work—thereby preventing the party who requested the changed work from later arguing that notice provisions were not complied with.
In the case, Jackson Dean, the prime contractor, hired Cascade to perform excavation work on a project to build a new Costco Corporate headquarters. Due to the Covid-19 pandemic and other issues, Jackson Dean directed resequencing, which required Cascade to perform excavation concurrent to dewatering. Jackson Dean also required deeper-than-planned excavation under one of the buildings.
Read the court decisionRead the full story...Reprinted courtesy of
Wendy Rosenstein, Ahlers Cressman & Sleight PLLCMs. Rosenstein may be contacted at
wendy.rosenstein@acslawyers.com
Is Your Contract “Mission Essential?” Recovering Costs for Performing During a Force Majeure Event Under Federal Regulations
May 10, 2022 —
Joneis M. Phan & Sarah K. Bloom - ConsensusDocsFederal contractors have faced unprecedented challenges performing during the COVID-19 pandemic. Additional costs have included delays and inefficiencies, site closures, quarantines, unavailability of supplies and materials, and full shutdowns of subcontractor operations. For contractors performing under fixed price contracts, the cost impact of COVID-19 was likely severe.
The Federal Acquisition Regulation (“FAR”) recognizes “epidemics” as a force majeure event that may excuse non-performance. Many federal contracts include some version of the Default clause, which prevents the government from terminating a contractor for default due to impacts of force majeure events that are beyond a contractor’s control, such as an epidemic. See, e.g., FAR 52.249-10. See also Pernix Serka Joint Venture v. Dep’t of State, CBCA No. 5683 (Apr. 20. 2020). The Default clause, however, operates as a shield from liability, not a sword authorizing recovery. Contractors are now left wondering whether any avenue exists to recover additional costs incurred after performing in the face of the COVID-19 pandemic.
In response to a likely influx of claims and requests for equitable adjustment due to COVID-19 impacts, the federal government largely took the position that contractors were entitled to extensions of time, but not to additional costs. This article explores the avenues that may be available for contractors to recover costs for performing during a force majeure event that would otherwise be non-compensable.
Reprinted courtesy of
Joneis M. Phan, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs and
Sarah K. Bloom, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs).
Mr. Phan may be contacted at jphan@watttieder.com
Ms. Bloom may be contacted at sbloom@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Just When You Thought the Green Building Risk Discussion Was Over. . .
May 25, 2020 —
Christopher G. Hill - Construction Law MusingsAs a reader of Construction Law Musings, you no doubt realize that I am a big proponent of “green” or sustainable building. I have also been known to sound a bit like Eeyore when discussing the charge into the breach of green building without considering the potential risks. Thankfully, and despite some of the risk predictions made here (and elsewhere for that matter) there have not been but so many major court cases relating to these risks.
However, as a recent article in ENR Magazine warns, this lack of litigation does not mean that you should let your guard down. Just because the economy, warnings by attorneys and others, and possible lack of financial incentive to sue have kept the litigation numbers down does not mean that the risks have gone away. LEED requirements, time horizons and other risks that have become evident during the process of vetting green building contracts and practices still must be dealt with in contracts and insurance policies. These risks are well laid out in the ENR article and in other places here at Musings so I won’t outline them in detail here.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com