New Washington Law Nixes Unfair Indemnification in Construction Contracts
April 25, 2012 —
Douglas Reiser, Builders Council BlogContractual fairness ? it is part of my mantra. If you read the blog, you probably know that I preach brevity, balance and clarity in contracting. The State of Washington did well to finally eliminate something that has angered me for quite some time ? unfair indemnification.
One of my favorite construction contract revisions is mutual indemnification. Many “up the chain” contractors and owners are going to stick you with a unilateral indemnification clause that protects them for just about everything, including their own fumbling of a project. Adding mutual indemnification provides some balance, and keeps parties reliant upon each other for success on the job site.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Client Alert: Absence of a Court Reporter at a Civil Motion Hearing May Preclude Appellate Review
November 26, 2014 —
Angela S. Haskins & Blythe Golay - Haight Brown & Bonesteel LLPA California Court of Appeal expressed its concern over the due process implications of reviewing a trial court's decision that incorporated reasons that were not documented due to the absence of a court reporter. In Maxwell v. Dolezal (No. B254893, filed 11/4/14), the court cautioned that although the lack of a transcript did not preclude its review of an order sustaining a demurrer, the case was an exception because the operative complaint and demurrer were sufficient to permit effective appellate review.
The plaintiff in Maxwell, acting in pro per, had filed an action for invasion of privacy and breach of contract. The plaintiff alleged that the defendant had used his photograph and website without his consent and that he did not receive the money, food and housing in exchange for the intellectual property rights per their agreement. The defendant demurred on the grounds that the complaint was uncertain and it could not be ascertained from the pleading whether the contract was written, oral, or implied. At the hearing on the demurrer, no court reporter was present. Nonetheless, the trial court's minute order explicitly sustained the demurrer "[f]or the reasons stated in open court," without further elaborating. The trial court also denied the plaintiff further leave to amend on the ground that he was unable to articulate in open court a reasonable basis for any additional allegations that would remedy the deficiencies. The court of appeal noted that it was "profoundly concerned about the due process implications of a proceeding in which the court, aware that no record will be made, incorporates within its ruling reasons that are not documented for the litigants or the reviewing court."
Reprinted courtesy of
Angela S. Haskins, Haight Brown & Bonesteel LLP and
Blythe Golay, Haight Brown & Bonesteel LLP
Ms. Haskins may be contacted at ahaskins@hbblaw.com; Ms. Golay may be contacted at bgolay@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Lawsuits Hinted for Dublin, California
February 07, 2013 —
CDJ STAFFWithout naming the community, the blog Around Dublin says that a condo community in Dublin, California may be prepping for a construction defect lawsuit. According to the article, the problems include a façade peeling away from the building, cracks in walls and granite countertops, and issues with both the HVAC systems and the plumbing. The homeowners association is said to have insufficient reserve funds to address the problems.
Read the court decisionRead the full story...Reprinted courtesy of
First Railroad Bridge Between Russia and China Set to Open
August 06, 2019 —
Saibal Dasgupta - Engineering News-RecordWork was completed on the first-ever railroad bridge connecting Russia to China in early April, as Russian engineers installed the final steel beam in its section of the structure over the river called the Amur in Russian and the Heilongjiang. China finished its part of the work last October, as the structure successfully spanned the world's 10th longest river, which markets the boundary between the two countries. Officials say the bridge will open for public use after the necessary inspections in July this year.
Read the court decisionRead the full story...Reprinted courtesy of
Saibal Dasgupta, ENRENR may be contacted at
ENR.com@bnpmedia.com
Colorado Senate Revives Construction Defects Reform Bill
January 04, 2018 —
BEVERLEY BEVENFLOREZ - CDJ STAFFOriginally Published by CDJ on March 1, 2017
A re-booted construction defects reform bill recently passed its first Senate committee, according to the Denver Business Journal. Next, Senate Bill 156, sponsored by Sen. Owen Hill, R-Colorado Springs, heads to the Senate floor for debate.
SB 156 “would require that condominium owners alleging construction defects take their disputes to arbitration or mediation if requested by builders,” the Denver Business Journal reported. “It also would require that homeowners be informed of the consequences of filing legal actions over purported disputes and that a majority of all owners in a condominium complex vote to proceed with legal action, rather than just a majority of homeowners association board members.”
However, it is almost identical to the failed measures that were introduced in 2014 and 2015.
Homeowners association group members and owners of defective condominiums argued against the measure, stating “that the effort would not improve the quality of building in the state, but simply would block aggrieved Coloradans from taking their complaints before a jury of their peers.”
Proponent of the bill, Tom Clark, CEO of Metro Denver Economic Development Corp., said “that Denver’s housing costs have risen since the first bill was introduced in 2013 to the sixth-most-expensive in the country – and are tops for any metro area not on a coast.”
Read the court decisionRead the full story...Reprinted courtesy of
Another Case Highlighting the Difference Between CGL Policies and Performance Bonds
January 07, 2015 —
David M. McClain – Colorado Construction Litigation During the summer of 2011, Ellis Construction hired Cool Sunshine Heating & Air Conditioning to install the HVAC systems in a single-family home it was building for Gary Doberman and Ellen Robertson in Boulder, Colorado. The homeowners took issue with much of the work performed on their home and tried to negotiate directly with Ellis Construction. When those negotiations broke down, the homeowners sent a notice of claim pursuant to the Construction Defect Action Reform Act, C.R.S. § 13-20-801, et seq. One of the defects alleged in the notice of claim was that the SEERS 13 compressor installed by Cool Sunshine was inappropriate for the system and that because it was installed to run on only one stage, it did not meet the City of Boulder’s code requirements for noise levels. The homeowners therefore requested that the compressor be replaced with a SEERS 20 compressor, which would comply with the Boulder City Code.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
The Need to Be Specific and Precise in Drafting Settling Agreements
December 30, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCThe case of Bituminous Casualty Corp. v. Hartford Casualty Insurance Corp., 2013 WL 452374 (D. Colo. February 6, 2013) is instructive as an example of both the confusion and resulting escalation of litigation that can result from a lack of clarity in settlement negotiations. This is particularly true where parties settle outside of their insurance coverage, and/or without notifying their insurer(s), which have denied coverage.
The case involved coverage litigation following settlement of a multi-party construction defect case involving the Rivergate multi-family residential development in Durango, Colorado. The condominium owners association sued, among others, the developer (Rivergate Lofts Partners, hereafter “RLP”) and the general contractor (Genex Construction, LLC, hereafter “Genex”). This follow-on case involved the insurers for RLP (“Hartford”) and Genex (“Bituminous”). The coverage dispute was complicated by the Bituminous allegations that Hartford insured Genex in its alleged role as a manager for RLP, as part of Hartford’s insurance of RLP more generally.
The underlying facts were that Hartford denied insurance coverage and defense to Genex/Bituminous. The underlying construction defect case went to mediation, with the COA, RLP, and Genex all in attendance with their respective insurer representatives, and coverage counsel. While the evolving facts of that mediation were later disputed as to their motives, intentions, and the contemporaneous knowledge of the parties, the facts reflected in documents were fairly clear.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.W. Berkeley Mann, Jr. can be contacted at
mann@hhmrlaw.com
Seventh Circuit Confirms Additional Insured's Coverage for Alleged Construction Defects
August 10, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit held that the underlying complaint alleged an occurrence by asserting that the painting subcontractor was negligent in causing damage to the building. Westfield Ins. Co. v. Nat'l Decorating Serv., Inc., 2017 U.S. App. LEXIS 12516 (7th Cir. July 13, 2017).
McHugh Construction, the general contractor for construction of a 24 story condominium building in Chicago, retained National Decorating Service, Inc. as a subcontractor to perform all of the painting work. This meant National Decorating would paint the exterior of the building with a protective coating that was a waterproof sealant.
After completion, the building's board of managers sued McHugh, National Decorating, and others for damages resulting from faulty workmanship. The third amended complaint alleged: (1) significant cracking of the exterior concrete walls, interior walls, and ceilings; (2) significant leakage through the exterior concrete walls, balconies, and windows; (3) defects to the common elements of the building; and (4) damage to the interior ceilings, floors, interior painting, drywall, and furniture in the units.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com