Someone Who Hires an Independent Contractor May Still Be Liable, But Not in This Case
April 18, 2023 —
Katherine Dempsey - The Subrogation StrategistIn Allstate Veh. & Prop. Ins. Co. v. Glitz Constr. Corp., 2023 N.Y. App. Div. LEXIS 1180, 2023 NY Slip Op 01171, the Supreme Court of New York, Appellate Division, Second Department (Appellate Court), considered whether a contractor could be found liable for its subcontractor’s alleged negligence in causing injury to a homeowner’s property. The homeowner’s insurer, as subrogee of the homeowner, sought to recover damages from the contractor despite an allegation that the subcontractor – an independent contractor – caused the injury to the homeowner’s property. Finding that there was no evidence that any of the exceptions to the non-liability rule related to hiring independent contractors applied, the Appellate Court affirmed the lower court’s decision granting judgment in favor of the contractor.
In this case, the homeowner hired the contractor (defendant) to convert her garage area into a bedroom and an office. The defendant later hired a subcontractor to perform the electrical rough-in work. At trial, the homeowner’s insurer (plaintiff) presented evidence that the subcontractor, who damaged an existing wire with a drill bit, caused an electrical failure that resulted in a fire. The defendant argued that it could not be held liable for the subcontractor’s alleged negligence because the subcontractor was an independent contractor and, on appeal, the Appellate Court agreed.
Read the court decisionRead the full story...Reprinted courtesy of
Katherine Dempsey, White and Williams LLPMs. Dempsey may be contacted at
dempseyk@whiteandwilliams.com
Enforcement Of Contractual Terms (E.G., Flow-Down, Field Verification, Shop Drawing Approval, And No-Damage-For-Delay Provisions)
May 04, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhat you contractually agree to matters, particularly when you are deemed a sophisticated entity. This means you can figuratively live or die by the terms and conditions agreed to. Don’t take it from me, but it take it from the Fourth Circuit’s decision in U.S. f/u/b/o Modern Mosaic, Ltd. v. Turner Construction Co., 2019 WL 7174550 (4th Cir. 2019), where the Court started off by stressing, “One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced.” Id. at *1.
This case involved a dispute between a prime contractor and its precast concrete subcontractor on a federal project. The subcontractor filed a Miller Act payment bond lawsuit. The trial court ruled against the subcontractor based on…the subcontract’s terms! So, yes, what you contractually agree to matters.
Example #1 – The subcontractor fabricated and installed precast concrete panels per engineering drawings. However, the parking garage was not built per dimensions meaning the panels it fabricated would not fit. The subcontractor had to perform remedial work on the panels to get them to fit. The subcontractor pursued the prime contractor for these costs arguing the prime contractor should have field verified the dimensions. The problem for the subcontractor, however, was that the subcontract required the subcontractor, not the prime contractor, to field verify the dimensions. Based on this language that required the subcontractor to field verify existing conditions and take field measurements, the subcontractor was not entitled to its remedial costs (and they were close to $1 Million). Furthermore, and of importance, the Court noted that the subcontract contained a flow down provision requiring the subcontractor to be bound by all of the terms and conditions of the prime contract and assume those duties and obligations that the prime contractor was to assume towards the owner. While this flow-down provision may often be overlooked, here it was not, as it meant the subcontractor was assuming the field verification duties that the prime contractor was responsible to perform for the owner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Ways of Evaluating Property Damage Claims in Various Contexts
February 18, 2020 —
Bremer Whyte Brown & O'Meara LLPPotential damages in a lawsuit may come in many forms depending on the facts of the case. Common damages include medical expenses, loss of earnings, property loss, physical pain, and mental suffering. Of the many damages Plaintiffs may claim, one of the most prevalent and recognizable is property damage. This article briefly discusses these types of damages which fall under two major categories – Real Property and Personal Property.
Broadly speaking, “real property” means land, and “personal property” refers to all other objects or rights that may be owned. Ballentine’s Law Dictionary defines “real property” as: “Such things as are permanent, fixed, and immovable; lands, tenements, and hereditaments of all kinds, which are not annexed to the person or cannot be moved from the place in which they subsist. . . .” (Ballentine’s Law Dict. (3d ed. 2010).) “Personal property” is defined as: “Money, goods, and movable chattels . . . . All objects and rights which are capable of ownership
except freehold estates in land, and incorporeal hereditaments issuing thereout, or exercisable within the same.” (Id. (emphasis added).)
Real Property
Real property may be damaged or “harmed” through trespass, permanent nuisance, or other tortious conduct. The general rule is that Plaintiffs may recover the lesser of the two following losses: (1) the decrease in the real property’s fair market value; or (2) the cost to repair the damage and restore the real property to its pre-trespass condition plus the value of any lost use. (Kelly v. CB&I Constructors, Inc.) However, an exception to this general rule may be made if a Plaintiff has a personal reason to restore the real property to its former condition, sometimes called the “personal reason” exception. In such cases, a Plaintiff may recover the restoration costs even if the costs are greater than the decrease in the real property’s value, though the restoration cost must still be “reasonable” in light of the value of the real property before the injury and the actual damage sustained.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Attorney Risks Disqualification If After Receiving Presumptively Privileged Communication Fails to Notify Privilege Holder and Uses Document Pending Privilege Determination by Court
May 03, 2017 —
David W. Evans & Stephen J. Squillario - Haight Brown & Bonesteel LLPIn McDermott Will & Emery LLP v. Superior Court (4/18/2017 – No. G053623), the Fourth Appellate District, in a 2-1 decision, considered two distinct issues: 1. Whether the attorney-client privilege for a confidential e-mail communication between a client and his attorney had been waived by the client’s inadvertent disclosure of the communication to a third party; and 2. Whether the opposing counsel’s failure to respect the claimed privilege as to the inadvertently produced document or to follow the rules for handling such documents set forth in State Compensation Ins. Fund v WPS, Inc. (1999) 70 Cal.App.4th 644 (State Fund) supported the trial court’s disqualification of counsel and his law firm.
This case arose from an intra-family dispute over the deceased matriarch’s substantial investment holdings, a related probate matter, and two subsequent legal malpractice actions. The opinion sets forth in great detail the facts surrounding the claimed inadvertent disclosure by the client (i.e., the privilege holder) of the subject attorney-client e-mail communication, its subsequent dissemination to, and use by, the client’s family members, the ultimate receipt and review by an opposing family member’s counsel, the efforts by the client’s counsel to assert the privilege and “claw-back” the document, and in the face of this privilege claim, the opposing counsel’s extensive use of the document during discovery, including depositions, in the legal malpractice actions. The opposing counsel, who had received the subject document from his own client, had independently concluded that the clearly privileged document lost its privileged status, believing that the privilege had been waived either because of disclosure to third parties or that his obligation to return inadvertently disclosed documents only applied to those produced in litigation during discovery. As a result, the opposing counsel refused all demands for the return or destruction of the document and insisted upon continuing to use it. This dispute finally came to a head over two years after the client’s disclosure in the context of the client’s motion for a judicial determination that the document was privileged (which the trial court granted) and then a motion to disqualify the opposing counsel (which the trial court also granted); both decisions were eventually reviewed by the appellate court.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Rio Olympic Infrastructure Costs of $2.3 Billion Are Set to Rise
January 31, 2014 —
Tariq Panja and David Biller – BloombergBrazilian authorities announced 5.6 billion reais ($2.3 billion) will be spent on infrastructure directly related to the 2016 Rio de Janeiro Olympic Games and those costs will rise as projects are added.
Yesterday’s announcement comes months behind schedule, and after pressure on public bodies to reveal exactly how much it will cost for Rio to be the first South American city to host the quadrennial showpiece. Delays and cost overruns to several projects related to this year’s soccer World Cup have sharpened the focus on the Olympics.
“We are committed to being on schedule,” Sports Minister Aldo Rebelo said at a press conference in Rio to announce the spending plans. “It is the first time we have a consortium of three levels of government. It is in an effort to ensure the success and execution of all the commitments to deliver the Olympics in Rio in 2016.”
Mr. Panja may be contacted at tpanja@bloomberg.net and Mr. Biller may be contacted at dbiller1@bloomberg.net.
Read the court decisionRead the full story...Reprinted courtesy of
Tariq Panja and David Biller, Bloomberg
Distressed Home Sales Shrinking
October 22, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Molly Boesel in CoreLogic, “Distressed sales (REO and short sales) accounted for 11.2 percent of total home sales in August 2014, the lowest share since December 2007 and a strong improvement from the same time a year ago when this category made up 15 percent of total sales.”
Michigan had the largest amount of distressed sales, with 25.5 percent in August, while California “saw the largest improvement from peak distressed sales share of any state, falling 55.3 percent from the January 2009 peak share of 67.4 percent.”
Read the court decisionRead the full story...Reprinted courtesy of
Where Did That Punch List Term Come From Anyway?
March 27, 2019 —
Duane Craig - Construction InformerI’ve often wondered just where the term “punch list” came from, and I’ve found a few sources that seem to make sense, while others not so much.
One person claims it came from the telephone installer process of “punching down” terminals on a block. That seems a bit of a stretch though. A blog writer said it had to do with the term ‘punch’ since it means to “punch something up” as in fix it.
Another blog writer thought it had something to do with a long forgotten practice. Apparently subcontractors used to each have their own hole punches that would punch a hole with a shape unique to them. They would use these punches to indicate they had corrected the deficiency that was their responsibility.
Read the court decisionRead the full story...Reprinted courtesy of
Duane Craig, Construction Informer
Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com