The Biggest Change to the Mechanics Lien Law Since 1963
December 08, 2016 —
Wally Zimolong – Supplemental ConditionsThe New Year will bring with it the biggest change to Pennsylvania’s Mechanics Lien Law since the current law was passed in 1963. These changes will impact owner, contractors, and subcontractors equally. However, the biggest benefits will probably be for real estate developers and other project owners.
On December 31, 2016, Pennsylvania will go live with a website known as the State Construction Notices Directory. On that date, owners will have the option of making projects costing $1,500,000 or more “searchable projects.” An owner makes a project a searchable project by filing with the Notices Directory a “Notice of Commencement” before works begins. The Notice of Commencement must include the name, address, and email address of the contractor, full name and location of the searchable project, the county where the project is located, a legal description of the searchable property, and the name address, and email address of the searchable project owner. Importantly, the owner must also post a copy of this Notice of Commencement at the project site.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Lakewood Introduced City Ordinance to Battle Colorado’s CD Law
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Denver Post, the Lakewood City Council “introduced an ordinance that would make it more difficult for homeowners associations to sue developers for construction defects and give builders more opportunity to fix problems before litigation begins.” A hearing and final vote is scheduled for October 13th.
"If there are defects, we want to get them fixed rather than dragging this through the courts for years," Lakewood Mayor Bob Murphy told The Denver Post. Murphy believes the ordinance will bring “more diverse housing options to Lakewood, especially around stations along the Regional Transportation District’s West Rail Line.” Lakewood’s City Planner Travis Parker also declared that the defects law is to blame for the lack of condos in the area.
However, some believe that “Lakewood is overstepping its bounds as a home-rule city,” according to The Denver Post. "What they're trying to do is use an ordinance to circumvent state law in order to make it impossible for homeowners to seek redress against builders for defects," Molly Foley-Healy an attorney who serves as legislative liaison for the Community Associations Institute's Legislative Action Committee told the Post. “Mayor Murphy needs to incentivize quality construction in Lakewood instead.”
Read the court decisionRead the full story...Reprinted courtesy of
Toronto Contractor Bondfield Wins Court Protection as Project Woes Mount
May 27, 2019 —
Scott Van Voorhis - Engineering News-RecordA Toronto area contractor at the center of a series of delays to major projects in Ontario, including a $139-million hospital expansion, has won court protection from its creditors. The Ontario Superior Court earlier this month granted Bondfield Construction Co.’s application for protection, court records show.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENR
General Contractor’s Excess Insurer Denied Equitable Contribution From Subcontractor’s Excess Insurer
December 15, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Advent v. National Union Fire Ins. Co., etc. (No. H041934 filed 12/6/16), a California appeals court refused to order a subcontractor’s excess insurer to contribute to a general contractor’s excess insurer because the general contractor did not qualify as an additional insured of the subcontractor’s insurer, and the policy wording made the subcontractor’s excess insurer second level excess above the general contractor’s own excess insurance.
Advent was the general contractor on a housing development and Johnson was a sub-subcontractor providing concrete on perimeter walls. A Johnson employee dispatched to retrieve plywood dumped between some of the buildings somehow fell down an open stairwell inside one of the unfinished buildings and suffered serious injury. He sued Advent and others for negligence, but could not remember how he fell.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What to Look for in Subcontractor Warranty Endorsements
February 03, 2020 —
David M. McLain – Colorado Construction LitigationWith increasing frequency in the construction defect cases we defend, we are seeing commercial general liability insurance policies with “subcontractor warranty” endorsements. Also known as contractor or subcontractor special conditions, these endorsements could have severe and negative consequences for builders that do not comply with their requirements. In researching for this article, I reviewed six different endorsements used by six different carriers, all of which contained some or all of the following requirements:
- The builder must have signed subcontract agreements with its subcontractors that require subcontractors to hold harmless, i.e., defend and indemnify, the builder for “bodily injury” or “property damage” claims caused by their negligence.
- The subcontractors must maintain their own insurance with limits equal to or greater than the limits in the builder’s own policy, with limits of at least $1 million per occurrence.
- The subcontractors’ insurance must not exclude the work being performed for the builder, e.g., the excavator’s policy cannot exclude earth movement claims, the subcontractor’s policy cannot exclude residential construction.
- The subcontractors must maintain their own workers’ compensation and/or employer’s liability insurance.
- The subcontractors must provide the builder with an endorsement or a certificate of insurance indicating that the builder has been added to the subcontractors’ insurance as an additional insured.
- The subcontractors must provide the builder with an endorsement or a certificate of insurance indicating that their insurance carriers have agreed to provide waivers of subrogation in favor of the builder.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
California Contractors: Amended Section 7141.5 Provides Important License Renewal Safety Net
July 25, 2021 —
Amy L. Pierce, Mark A. Oertel, John Lubitz & Adam B. Wiens - Lewis BrisboisUnder California’s Contractors State License Law, Cal. Bus. & Prof. Code §§ 7000 et seq., contractors’ licenses expire two years from the last day of the month in which the license was issued or two years from the date on which the renewed license last expired. The Contractors State License Board (CSLB) sends licensees a renewal application 60 to 90 days in advance of the date the license is set to expire. Even with various controls in place, mistakes happen and a renewal application filing deadline can be missed.
During the August 5-6, 2019 Executive, Licensing, and Legislative Committee Meetings, the CSLB discussed proposed amendments to Section 7141.5 to reduce both the burden on it to review applications for retroactive renewal of a license that had not been timely submitted and to provide contractors with some relief from the high burden to establish “the failure to renew was due to circumstances beyond the control of the licensee.” Not long after, the CSLB’s Board of Directors gave staff approval to seek an author for the bill and, on September 29, 2020, Governor Newsom signed Senate Bill 1474 into law, which includes the CSLB’s proposed amendments to Section 7141.5, effective January 1, 2021.
Reprinted courtesy of
Amy L. Pierce, Lewis Brisbois,
Mark A. Oertel, Lewis Brisbois,
John Lubitz, Lewis Brisbois and
Adam B. Wiens, Lewis Brisbois
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Mr. Wiens may be contacted at Adam.Wiens@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Contract Change #9: Owner’s Right to Carry Out the Work (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn prior versions of the General Conditions, if a contractor defaulted and the Owner (after giving notice) opted to cure by carrying out the work itself, an appropriate Change Order would be issued. However,
a Change Order is a contract that requires an agreement by both the Owner and Contractor, and, obviously, Contractors were reluctant to agree that they were in default and responsible for a deductive change order.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Partner Jonathan R. Harwood Obtained Summary Judgment in a Case Involving a Wedding Guest Injured in a Fall
December 30, 2019 —
Jonathan R. Harwood - Traub Lieberman PerspectivesOn September 30, 2019, Traub Lieberman partner Jonathan Harwood obtained summary judgment in an action involving a guest injured in a fall at a wedding. Traub Lieberman’s client owned the property where the fall occurred. Plaintiff fell while exiting a row of seats after the bridal party had recessed down the aisle. Plaintiff claimed that she tripped over the raised side of a paper runner that had been placed in the aisle at the property. Plaintiff brought an action against Traub Lieberman’s client (the owner of the building) and the florist that had provided the runner. The owner had provided the bridal party with access to the property but did not assist in the set up for the wedding or have any employees present during the ceremony. The florist had supplied the runner for the wedding. The florist commenced a third-party action against the bride, whose wedding party had actually placed the runner in the aisle. Plaintiff asserted that the runner had become bunched and crumpled during the ceremony, creating a dangerous condition. She further asserted that the owner was responsible for her injuries since the dangerous condition existed on its property and it should have an employee present to insure no dangerous conditions existed.
During the course of discovery, Mr. Harwood established that no one representing the owner was present during the wedding, had any involvement in the placement of the runner or had received any complaints about the runner. In support of the motion for summary judgment Mr. Harwood introduced pictures showing, in conjunction with deposition testimony, that there were no problems with the runner minutes before plaintiff’s fall. Mr. Harwood also argued that the alleged defect did not involve the property itself, absolving the owner of any obligation to plaintiff. In granting the motion for summary judgment, the court held that evidence and testimony showed that the owner neither created the condition nor had actual or constructive notice that any dangerous condition existed. The court also held that there the owner did not have any duty to have a representative present during the wedding since the property itself was not dangerous or defective. Finally, the court held that the condition of the runner was open and obvious and not inherently dangerous.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan R. Harwood, Traub LiebermanMr. Harwood may be contacted at
jharwood@tlsslaw.com