Federal Interpleader Dealing with Competing Claims over Undisputed Payable to Subcontractor
September 28, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhat do you do if you are holding undisputed money owed to a subcontractor? Well, you make an effort to pay it or tender it! Right? I am never a fan of a client holding undisputed sums without a legitimate contractual basis.
There are circumstances, however, where the effort to pay an undisputed payable is not so easy. In fact, it is challenging, as in the below case example where the subcontractor filed for an Assignment for the Benefit of Creditors (referred to as an “ABC”). An ABC, in a nutshell, allows an insolvent entity to file an insolvency action in state court governed by state law and choose its assignee (versus a federal bankruptcy action governed by federal law where a trustee is appointed). One major difference is that there is no automatic stay in an ABC as there is in a federal bankruptcy action. Thus, the insolvent entity can still be sued, but, while that entity is in an ABC, there are many creditors that will not be able to enforce a judgment. (See Florida Statute Ch. 727).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Drafting the Bond Form, Particularly Performance Bond Form
July 14, 2016 —
David Adelstein – Florida Construction Legal UpdatesOftentimes, when it comes to payment and performance bonds (in particular), the bond forms are drafted by the obligee. For example, an owner (as the obligee) may draft the bond forms that it wants its general contractor’s surety to execute. And, a general contractor (as the obligee) may draft the bond forms that it wants its subcontractors’ sureties to execute. As an obligee, it is always beneficial to draft the bond form (particularly the performance bond) that you want the surety to execute. The bond is to benefit you—the obligee—so having a hand in creating conditions to trigger the application of the bond is important, specifically when it comes to triggering a performance bond upon the bond-principal’s default.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Scotiabank Is Cautious on Canada Housing as RBC, BMO Seek Action
April 12, 2021 —
Shelly Hagan & Erik Hertzberg - BloombergBank of Nova Scotia, Canada’s third-largest lender, waded into the burgeoning debate over whether Justin Trudeau’s government should take immediate steps to cool the nation’s hot housing market, issuing a report that cautioned against rushing to implement new constraints.
In a report released Sunday, Scotiabank’s chief economist Jean-Francois Perrault said the recent run-up in home prices nationally over the past year was in large part driven by sluggish supply that failed to keep up with higher demand -- a trend that could reverse itself as new sellers enter the market in coming weeks. If the government does decide to take action, it should target housing speculators, he said.
Reprinted courtesy of
Shelly Hagan, Bloomberg and
Erik Hertzberg, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Bridges Crumble as Muni Rates at Least Since ’60s Ignored
June 26, 2014 —
William Selway and Brian Chappatta – BloombergNo state is needier than West Virginia when it comes to fixing crumbling highways, airports and water works, with annual repair needs of $1,035 per resident that’s three times the national average.
Yet even with borrowing costs hovering close to four-decade lows, lawmakers rejected a January proposal to sell $1 billion of bonds to repair roads that run through the Appalachian Mountains. Budget cuts were a more immediate concern, they said.
Across the U.S., localities are refraining from raising new funds in the $3.7 trillion municipal-bond market after the worst financial crisis since the Great Depression left them with unprecedented deficits. Rather than take advantage of Federal Reserve (FDTR) policy that’s held benchmark interest rates at historic lows since December 2008, they’re repaying obligations by the most on record.
Mr. Selway may be contacted at wselway@bloomberg.net; Mr. Chappatta may be contacted at bchappatta1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
William Selway and Brian Chappatta, Bloomberg
Honoring Veterans Under Our Roof & Across the World
November 15, 2017 —
Newmeyer & Dillion, LLPNovember 11, 2017 - In honor of Veterans Day, we would like to take time to acknowledge, honor and thank those who have served in the United States Armed Forces. We are also proud to recognize eleven of our own who have served our great country.
Ben Ammerman – United States Navy
Philip Kopp – United States Air Force
Ryan Manning – United States Marine Corps
Jason Morris – United States Marine Corps
Tyson Nakagawa - United States Marine Corps
Richard Protzmann - United States Marine Corps
Francis Quinlan - United States Marine Corps
Louis “Dutch” Schotemeyer - United States Marine Corps
Christina Soto-Maynez – United States Army
Michael Studenka - United States Marine Corps
Paul Tetzloff - United States Marine Corps
About Us
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Performance Bonds: Follow the Letter of the Bond and Keep The Surety Informed
December 06, 2021 —
Bill Shaughnessy, Jones Walker, LLP - ConsensusDocsConstruction surety bonds are risk management tools utilized by parties on large construction projects. However, bonds are not insurance, and a surety is not an “insurer” of the project. Different from insurance, a surety’s obligation to act typically arises if the principal fails to perform in accordance with the construction contract, and if the claimant satisfies the conditions precedent to enforcing the bond.[1]
This article focuses exclusively on performance bonds on private projects,[2] and highlights practical considerations and surety defenses to enforcement of the performance bond.[3] Spoiler alert – the party making a claim on the bond must strictly adhere to the conditions precedent set forth in the bond throughout the construction project and when calling upon the surety to take action, otherwise the performance bond may be rendered void and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker, LLPMr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
Number of Occurrences Depends on Who is Sued
August 20, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to David L. Beck of Pillsbury Winthrop Shaw Pittman LLP (as published by Association of Corporate Counsel), an Oregon court “held that property damage incurred to a condominium project resulting from a myriad of construction defects constituted just one occurrence under the relevant excess general liability policy.”
In Chartis Specialty Ins. Co. v. American Contractors Ins. Co Risk Retention Group, et al., Chartis argued that “[b]ecause there were multiple defects/conditions resulting in property damage” there were also “multiple occurrences.” However, “[t]he court disagreed, finding that despite various defects, the property damages at issue arose from just one occurrence: the developers' failure to perform its duties.”
Read the court decisionRead the full story...Reprinted courtesy of
Wait! Don’t Sign Yet: Reviewing Contract Protections During the COVID Pandemic
April 13, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesAs the circumstances of the COVID pandemic change day by day, and we all rush to keep business moving where and when we can, companies should consider hitting the “pause button” before renewing or executing any new contracts. Developing contracts often takes considerable time and expense, and companies are not in the habit of reworking them often. A change in law may prompt a company to revisit their contract terms, but otherwise business is often carried out with a standard form contract for a period of years. With the COVID pandemic affecting nearly every business and industry, life is not business as usual, and companies should make sure their contracts consider what previously seemed like an unforeseeable event.
Force Majeure clauses are included in many contracts to excuse contract performance when made impossible by some unforeseen circumstance. These clauses typically fall under two categories: general and specific. General force majeure clauses excuse performance if performance is prevented by circumstances outside the parties’ control. By contrast, specific force majeure clauses detail the exhaustive list of circumstances (acts of god, extreme weather, war, riot, terrorism, embargoes) which would excuse contract performance. Force majeure clauses are typically interpreted narrowly. If your contract has a specific clause and pandemic or virus is not one of the listed circumstances it may not apply. Whether a particular existing contract covers the ongoing COVID pandemic will vary depending on the language of the contract.
Force majeure clauses previously made headlines when the great economic recession hit in 2008. A number of courts held that simple economic hardship was not enough to invoke force majeure. The inability to pay or lack of desire to pay for the contracted goods or services did not qualify as force majeure. In California, impossibility turns on the nature of the contractual performance, and not in the inability of the obligor to do it. (Kennedy v. Reece (1964) 225 Cal. App. 2d 717, 725.) In other words, the task is objectively impossible not merely impossible or more burdensome to the specific contracting party.
California has codified “force majeure” protection where the parties haven’t included any language or the circumstances in the clause don’t apply to the situation at hand. Civil Code section 1511 excuses performance when “prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary.” (Civ. Code § 1511.) What qualifies as a “superhuman cause”? In California, the test is whether under the particular circumstances there was such an insuperable interference occurring without the party's intervention as could not have been prevented by the exercise of prudence, diligence and care. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd. (1946) 29 Cal.2d 228, 238.)
If you find yourself in an existing contract without a force majeure clause, or the statute does not apply, you may consider the doctrine of frustration of purpose. This doctrine is applied narrowly where performance remains possible, but the fundamental reason the parties entered into the contract has been severely or substantially frustrated by an unanticipated supervening circumstance, thus destroying substantially the value of the contract. (Cutter Laboratories, Inc. v. Twining (1963) 221 Cal. App. 2d 302, 314-15.) In other words, performance is still possible but valueless. Note this defense is not likely to apply where the contract has simply become less profitable for one party.
Now that COVID is no longer an unforeseeable event, but rather a current and grave reality, a party executing a contract today without adequate protections may have a difficult time proving unforeseeability. Scientists are not sure whether warm weather will suppress the spread of the virus, as it does with the seasonal flu, but to the extent we get a reprieve during the summer we may see a resurgence of cases this Fall or Winter. Companies should take care in reviewing force majeure clauses, and other clauses tied to timely performance such as delay and liquidated damages before renewing or executing new contracts.
Your contract scenario may vary from the summary provided above. Please contact legal counsel before making any decisions. During this critical time, BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com