Homeowners Not Compelled to Arbitration in Construction Defect Lawsuit
January 06, 2012 —
CDJ STAFFA California appeals court has ruled that developers cannot enforce CC&Rs in a case where a developer cited an arbitration clause it had inserted into the CC&R. The homeowners are alleging construction defect and wished to sue the developer who claimed a right to this under the CC&Rs.
The Marina del Rey Argonaut reports that particular appeal dealt only with whether the developer could compel arbitration. The underlying construction defect issues will subsequently have to be determined at trial.
The attorney for the homeowners’ association, Dan Clifford, noted that “arbitration has to be agreed to by both parties.” The covenant was drafted by the developer and in addition to requiring arbitration, it had a clause that it could not be amended without the consent of the developers. The court ruled that CC&Rs “can be enforced only by the homeowners association, the owner of a condominium or both.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Crypto and NFTs Could Help People Become Real Estate Tycoons
June 21, 2021 —
Josh D. Morton - Gravel2Gavel Construction & Real Estate Law BlogBy using online cryptocurrency technologies like tokens and blockchains, people could participate in real estate transactions that are too unwieldy in the analog world. Soon, these technologies may let anyone with a few thousand dollars play tycoon and buy a part of a condo or iconic building.
NFTs, or non-fungible tokens—digital certificates that convey exclusive rights to something—is a new concept being applied to real estate, supporters say they will become standard in the industry.
“The NFT operates in many respects exactly like a deed would in real estate transactions,” said Josh Morton, a Real Estate special counsel at Pillsbury. “What a deed ordinarily does is give evidence of ownership to a piece of property.”
Read the court decisionRead the full story...Reprinted courtesy of
Josh D. Morton, PillsburyMr. Morton may be contacted at
josh.morton@pillsburylaw.com
Housing Starts Fall as U.S. Single-Family Projects Decline
February 18, 2015 —
Bloomberg News(Bloomberg) -- Builders broke ground on fewer U.S. residential construction projects in January as demand for single-family homes cooled from an almost seven-year high, signaling the rebound in housing remains uneven.
Housing starts declined 2 percent to a 1.07 million annual rate, following the prior month’s 1.09 million pace, a Commerce Department report showed Wednesday in Washington. The median forecast of 82 economists surveyed by Bloomberg was 1.07 million. Permits, a proxy for future construction, also fell.
Student debt, tight credit conditions and rising prices are probably preventing would-be first-time homebuyers from entering the market, which will damp construction. At the same time, a strengthening labor market and rising household formation may support building of rental units, underpinning residential real estate.
Nina Glinski may be contacted at nglinski@bloomberg.net; Shobhana Chandra may be contacted at schandra1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
JAMS Announces Updated Construction Rules
June 21, 2021 —
JAMSIrvine, Calif. – JAMS, the largest private provider of
alternative dispute resolution (ADR) services worldwide, is pleased to announce it has revised and updated its
Construction Arbitration Rules & Procedures and
Expedited Construction Arbitration Rules & Procedures, effective June 1. These Rules were updated to reflect the latest developments and trends in
construction arbitration.
In response to the transition to virtual and hybrid proceedings, Rule 22 makes explicit the arbitrator’s full authority to conduct the hearing in person, virtually or in a combined form, as well as with participants in more than one geographic location. To support access to case documents throughout the proceedings, Rule 8 aligns electronic filing and service with the functionality of JAMS Access, a centralized, secure online case management platform.
Additional rules were created or revised to clarify and strengthen the authority of the arbitrator. Key changes include allowing an arbitrator to withhold approval of any intended change in party representation that could compromise the proceedings or the final award, to set a hearing without consulting a party that he or she reasonably believes will not participate and to permit a party to file a motion for summary disposition of a claim if the arbitrator believes that party has demonstrated the motion is likely to succeed.
About JAMS – Local Solutions. Global Reach.
Founded in 1979, JAMS is the largest private provider of alternative dispute resolution services worldwide. JAMS successfully resolves and manages business and legal disputes by providing efficient, cost-effective and impartial ways to overcome barriers at any stage of conflict. JAMS offers customized in-person, virtual and hybrid resolution services locally and globally through a combination of industry-specific experience, first-class client service, the latest technology and highly trained mediators and arbitrators.
Read the court decisionRead the full story...Reprinted courtesy of
JAMS
Florida’s Statute of Limitations / Repose for Actions Founded on Construction Improvement Modified
April 25, 2023 —
David Adelstein - Florida Construction Legal UpdatesOn April 13, 2023, Florida’s all-important four-year statute of limitations–Florida Statute s. 95.11(3)(c)–relating to actions founded on construction of an improvement of real property was modified. This is a key statute of limitations for ALL construction practitioners because it also includes the statute of repose for latent construction defects.
At the bottom of this posting is the current version fo s. 95.11(3)(c) with the underlined section being recent additions. (They hyperlink above will identify the deletions and additions.) Important things to note:
- Statute of Repose. The statute of repose has been reduced from 10 years to 7 years. There is now an objective date for when the repose period commences: “within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Supreme Court of Canada Broadly Interprets Exception to Faulty Workmanship Exclusion
November 10, 2016 —
C. Lily Schurra – Saxe Doernberger & Vita P.C.In a recent policyholder-friendly decision, the Supreme Court of Canada found coverage under an exception to the faulty workmanship exclusion in an all-risk policy. The decision provided the insureds with millions to cover the cost of replacing the faulty work.
Read the court decisionRead the full story...Reprinted courtesy of
C. Lily Schurra, Saxe Doernberger & Vita P.C.Ms. Schurra may be reached at
cls@sdvlaw.com
Contractor’s Unwritten Contractual Claim Denied by Sovereign Immunity; Mandamus Does Not Help
September 22, 2016 —
David R. Cook Jr. – AHHC Construction Law BlogIn a very well-reasoned opinion, the Supreme Court of Georgia upheld the denial of a contractor’s unwritten-contract claim against a county based on sovereign immunity. Based on an alleged oral contract, Contractor built a sewer pumping station for the County in exchange for an interest in the station’s pumping capacity. When the County denied Contractor’s demand for an interest, he filed suit.
As noted in many prior posts, the Georgia constitution reaffirms sovereign immunity of the state – which the courts interpret to include counties. One common exception in the public works area is the Constitution’s “ex contractu clause,” which waives sovereign immunity for claims based on written contracts. Of course, a precondition to the waiver of sovereign immunity is the existence of a written contract – which Contractor did not have.
Applying these rules, the court affirmed the denial of Contractor’s claims based on contract and quasi contract. In the absence of a written contract, there can be no contractual claim against the County. The same rule applies for quasi-contractual claims.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com