Preliminary Notices: Common Avoidable But Fatal Mistakes
August 26, 2019 —
William L. Porter - Porter Law GroupIn the California building and construction industry, service of a “Preliminary Notice” is a prerequisite for Subcontractor and Supplier claims for payment through the Mechanics Lien, Stop Payment Notice and Payment Bond Claim process. Without proper drafting and service of a Preliminary Notice, these extremely valuable claims cannot be protected. Unfortunately, despite the vital importance of the Preliminary Notice, Subcontractors and Suppliers often make common self-defeating mistakes that make their Preliminary Notice efforts completely ineffective, resulting in loss of their claims rights. The purpose of this article is to list some of these common mistakes in the hope that the reader will avoid such mistakes, preserve the integrity of the Preliminary Notice, and protect the claims rights it makes available:
Not Sending out the Preliminary Notice Within 20 Days After Supplying Labor or Materials:
The protection of a Preliminary Notice begins 20 days before it sent out. This means that if a Subcontractor or Supplier claimant delivered $100,000 in materials on February 1, that same claimant must serve the Preliminary Notice on or before February 21 (the sooner the better), or the claimant will not be able to pursue an enforceable Mechanics Lien, Stop Payment Notice or Payment Bond claim for that $100,000. There are very few exceptions. Best practice: A Subcontractor or Supplier must send out the Preliminary Notice as soon as an agreement to provide work or materials to a California construction project is in place (See California Civil Code 8204).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
California Supreme Court Holds Insured Entitled to Coverage Under CGL Policy for Negligent Hiring
June 13, 2018 —
Traub Lieberman Straus & Shrewsberry LLP - TLSS Insurance Law BlogIn its recent decision in Liberty Surplus Ins. Corp. v. Ledesma & Meyer Constr. Co.,2018 Cal. LEXIS 4063 (Cal. June 4, 2018), the Supreme Court of California addressed the question of whether an insured’s negligent hiring, retention and supervision of an employee who intentionally injured a third-party can be considered an occurrence under a general liability policy.
The insured, L&M, was the construction manager on a project at a middle school in California. It was alleged that one of its employees sexually abused a thirteen year old student during the course of the project. The student later brought a civil suit against L&M based on its negligent hiring, retention and supervision of the employee-perpetrator.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Straus & Shrewsberry LLP
Technology and the Environment Lead Construction Trends That Will Continue Through 2019
June 03, 2019 —
Ryan Gould - Construction ExecutiveThere are common factors that have always defined trends in the construction industry. Elements such as labor (be it shortages or surpluses), the economy and technology determine what gets built where, when and how.
These elements have led to the rise of entire philosophies to boost profits and maximize value, such as the lean construction movement. Often these trends appear in the form of answers that help construction companies eliminate waste, curb overproduction, use talent properly, manage inventory more effectively, boost process workflow, reduce defects, and help to plan and schedule projects more efficiently.
In 2019, two factors are driving trends that are overtaking the industry: technology and the environment. They’re not only informing construction industry trends today, but they’re going to last and evolve into the foreseeable future.
Offsite construction becomes standard
Obviously, this isn’t a new trend. The earliest origins of this method, at least in North America, date to colonists importing pre-packaged construction materials from Europe to the New World in the 17th century. Then there were the kit homes sold by Sears, Roebuck, and Co. at the turn of the 20th century. And of course, the trend reached its zenith in the World War II construction boom with pre-fab companies selling ready-to-go homebuilding components to builders.
Reprinted courtesy of
Ryan Gould, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Understanding the Details: Suing Architects and Engineers Can Get Technical
November 02, 2017 —
Steven M. Cvitanovic & Stephen M. Tye - Haight Brown & Bonesteel LLPBefore suing an architect or engineer for professional negligence, a plaintiff must obtain a “certificate of merit” (“Certificate”) under Code of Civil Procedure section 411.35. Boiled down to the basics, the Certificate declares that the attorney consulted with and received an opinion from an expert that a reasonable and meritorious case exists against said design professional. The Certificate must be filed before serving the complaint on any defendant, but can be filed within 60 days under certain circumstances. This rule was recently analyzed against another long-standing rule in California, known as the “relation-back doctrine.” Under the relation-back doctrine, a court will deem a later-filed pleading, such as an amended complaint, to be deemed filed at the time of an earlier complaint.
In Curtis Engineering Corp. v. Superior Court of San Diego County, No. D072046, (Cal. Ct. App. 10/23/17), the Fourth Appellate Court considered the interplay between section 411.35 and the relation-back doctrine, holding that a Certificate filed more than 60 days after filing the original pleading does not relate back to the filing of the original pleading.
Reprinted courtesy of
Steven Cvitanovic, Haight Brown & Bonesteel LLP and
Stephen Tye, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Law Bars Coverage for Construction Defects in Insured's Work
September 24, 2014 —
Tred R. Eyerly – Insurance Law HawaiiApplying Illinois law, the Seventh Circuit determined there was no coverage for faulty workmanship causing property damage to the insured's project. Nautilus Ins. Co. v. Board of Directors of Regal Lofts Condominium Ass'n, 2014 U.S. App. LEXIS 16250 (7th Cir. Aug. 21, 2014).
The developer converted a vacant building into a condominium. The construction was completed in 2000. The Condominium Board took control of the condo association on July 27, 2000. As early as May 2000, one homeowner was aware of water damage problems in the building. Other complaints surfaced. An investigation found that the exterior brick masonry walls were not fully waterproofed, which caused leaks. The investigation further showed that deteriorated conditions had likely developed over many years, even prior to the condominium conversion, but the present water penetration was caused by the inadequate restoration of the walls to a water-tight condition.
The underlying action was filed against the developer for failure to properly construct the exterior walls. The developer's carrier, Nautilus, denied coverage. In an amended complaint, the Board added a count of negligence. Again, Nautilus denied coverage. The Board's second amended complaint alleged that the developer's negligence had caused damage to personal property within the building, in addition to the interior of the building and the building itself. For the third time, Nautilus denied coverage and filed for declaratory relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Jason Feld Awarded Volunteer of the Year by Claims & Litigation Management Alliance
April 15, 2024 —
Linda Carter - Kahana FeldOn April 3, 2024, Kahana Feld’s Co-Founding Partner, Jason Feld was honored by the Claims & Litigation Management Alliance (CLM) with the Inaugural Volunteer of the Year award.
The CEO of CLM, Ronna Ruppelt stated, “The new CLM Volunteer of the Year award honors dedicated members who passionately serve the CLM community. Jason’s service spans over a decade as both the President and Director of Events for the Orange County Chapter. Under his guidance, this chapter has flourished – not only educating and connecting the CLM community but rallying members to give back to the local community through service events in the process. Jason is also a frequent writer, speaker, and contributor for CLM events, and we are proud to honor him as our inaugural CLM Volunteer of the Year.”
Mr. Feld is a renowned nationwide construction claims leader who actively speaks at industry events. He serves as panel counsel for many prominent insurance carriers and provides personal counsel for multiple national and regional builders, developers, and contractors. With his vast experience and expertise, Mr. Feld is a trusted authority in the field and is highly regarded for his legal representation.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Not in My Kitchen – California Supreme Court Decertifies Golden State Boring Case
November 26, 2014 —
Roger Hughes – California Construction Law BlogOn November 11, 2014, the California Supreme Court rejected the recent California Court of Appeals decision Golden State Boring & Pipe Jacking, Inc. v Eastern Municipal Water District, 228 Cal.App.4th 273 (2014) which we wrote about earlier by “decertifying” it (meaning that lawyers cannot cite to the case as legal precedent) The decertification removed a decision that added substantially to the confusion as to when an action on a payment bond is timely filed. Even though the decision was determined in accordance with pre-2014 statutes, the case was relevant precedent for construction attorneys when determining time deadlines for filing a claim on a bond.
Background
In July of this year, the California Court of Appeals for the Fourth Appellate District upheld a trial court’s granting of summary judgment against a project subcontractor Golden State Boring & Pipe Jacking, Inc. (GSB) who sued Safeco Insurance Company (Safeco) for unpaid contract amounts on a project payment bond issued by Safeco. Both at the trial level and on appeal Safeco successfully argued that GSB’s action on its payment bond claim was time barred by former California Civil Code Sections 3249 (now Section 9558), because it was filed more than six month after the period in which stop notices may be filed as provided by California’s Civil Code Section 3184 (now Section 9558).
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Design Firm Settles over Construction Defect Claim
July 31, 2013 —
CDJ STAFFA Pennsylvania township has announced that it has reached a settlement with the architectural firm that designed its administration building. Cee Jay Frederick Associates will be paying than $1.05 million to settle claims of defects in the design of the building.
West Whiteland’s administration building was completed in July 2007. The first leaks were noticed in November and December 2008. In response, the township stopped payments to the contractor, Magnum, Inc. Magnum sued, claiming that their work was not to blame for the leaks. Magnum joined the township in suing the design firm.
Although Cee Jay Frederick Associates will be paying the township to settle the claim, West Whiteland will be paying $75,000 of that back to the firm to settle outstanding bills that had been withheld during litigation.