Is Settling a Bond Claim in the Face of a Seemingly Clear Statute of Limitations Defense Bad Faith?
October 11, 2021 —
Christopher G. Hill - Construction Law MusingsWe have often discussed payment and performance bonds here at Construction Law Musings, most often in the context of payment bond claims relating to federal and state-owned. construction projects. A late 2020 case out of the Eastern District of Virginia federal court examined what happens after such a claim, in this case, based upon a developer’s subdivision bonds, is made and negotiations commence between the surety and the claimant. Specifically, Fidelity & Deposit Co. of Maryland v. Ransgate Corp., et. al. looked at claims for indemnity by a surety and the principal/indemnitors in the event that the Surety settled such a claim.
In the Ramsgate case, Surety provided two separate subdivision subcontract bonds to Ramsgate. Pursuant to those bonds and the indemnity clause of its indemnity agreement, the Surety sought reimbursement of its $80,000.00 settlement payment to the local building authority that it paid to resolve what was originally a claim for over $420,000.00 by the City. The project was started in 2002 and after many years of failures to complete (according to the City of Suffolk), the City made its claim for expenses in 2017. Ramsgate claimed that it completed the subdivisions in 2003.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Dreyer v. Am. Natl. Prop. & Cas. Co. Or: Do Not Enter into Nunn-Agreements for Injuries that Occurred After Expiration of the Subject Insurance Policy
January 20, 2020 —
Jean Meyer - Colorado Construction LitigationWhile Nunn-Agreements[1] may be appealing for both plaintiffs and defendants where an insurer unreasonably fails to defend a lawsuit, a recent opinion from The Honorable Marcia Krieger in the United States District Court of Colorado[2] (“Opinion”) demonstrates the importance of first confirming that there exists a viable insurance claim before proceeding with such a Nunn- Agreement.
The facts giving rise to the Opinion were as follows. In March 2015, a Homeowner couple (the “Homeowners”) suffered damages to their home resulting from a brushfire. Fortunately, the Homeowners were insured, they submitted their claim to their homeowners’ insurance carrier which was in effect at the time of the brushfire (the “Insurance Carrier”), and the Insurance Carrier paid the claim. Ostensibly as part of the Homeowners’ remediation efforts to their home they removed a large bush which left a hole in the ground. After paying the claim, in August 2015 the Insurance Carrier cancelled or elected not to renew the Homeowners’ policy. In October 2015, a repairman working on the Home (the “Repairman”) was injured after his ladder fell over allegedly because of the hole in the ground caused by the bush that had been removed.
As a result of injuries caused by the fall from the ladder, the Repairman brought suit against the Homeowners. In response to the Repairman’s claim, the Homeowners again tendered to their Insurance Carrier. This time, however, the Insurance Carrier denied coverage on the basis that the Repairman’s injuries occurred after the expiration of the relevant policy. Without insurance coverage, the Homeowner’s entered into a Nunn-Agreement with the Repairman, conceding liability, and assigning any claims they might have had against the Insurance Carrier in lieu of execution of any judgment against the Homeowners.
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
S&P 500 Little Changed on Home Sales Amid Quarterly Rally
July 01, 2014 —
Lu Wang and Jacob Barach – BloombergJune 30 (Bloomberg) --The Standard & Poor’s 500 Index was little changed, capping the longest string of quarterly gains since 1998, as a jump in pending home sales offset weaker-than-forecast manufacturing data.
D.R. Horton Inc. rallied 3.2 percent, leading gains among homebuilders. Yahoo! Inc. (YHOO) rose 2.6 percent after Piper Jaffray Cos. recommended buying the stock. MannKind Corp. jumped 9.6 percent as the maker of diabetes drugs rebounded from its worst week in two months. Allergan Inc. declined 2.7 percent following regulatory decisions on its drugs.
The S&P 500 fell less than 0.1 percent to 1,960.23 at 4 p.m. in New York. The equity benchmark gauge rose 4.7 percent for the quarter, a sixth consecutive advance. The Dow Jones Industrial Average lost 25.24 points, or 0.2 percent, to 16,826.60 today, trimming its quarterly advance to 2.2 percent. The Nasdaq Composite Index rose 0.2 percent, giving it a 5 percent increase for the three months.
Ms. Wang may be contacted at lwang8@bloomberg.net; Mr. Barach may be contacted at jbarach1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Lu Wang and Jacob Barach, Bloomberg
California Contractor Tests the Bounds of Job Order Contracting
March 01, 2021 —
Garret Murai - California Construction Law BlogMost contractors have heard of design-bid-build, design-build, construction manager at risk, and even public private partnerships, various project delivery methods, which, at their heart, focus on balancing the interests of the various parties involved in a construction project, from owners, to design professionals, to contractors. There’s one project delivery method you may not be as familiar with though: Job Order Contracting, also known by its acronym JOC.
JOC contracting is a project delivery method used on public works projects and has been authorized to be used by California K-12 school districts, community colleges, CalState universities, and the Judicial Council of California, which, among other things, is responsible for the construction of California state courts. It is intended to be used on smaller, independent, long-horizon project typically involving maintenance, repair and refurbishment. Think periodic maintenance of facilities.
JOC contracts are administered by public entities issuing a request for proposals. The public entity then awards a JOC contract to the lowest responsible bidder. The lowest responsible bidder then enters into a JOC contract with the public entity. JOC contracts typically have a duration of one (1) year and are limited to a total construction value of $4.9 million increased annually based on the Consumer Price Index. When entering into a JOC contract, a JOC contractor agrees to perform work at prices set forth in a Construction Task Catalog also known as a unit price book which includes current local labor, material and equipment costs. Unit prices are then adjusted by a “bid adjustment factor” based on the JOC contractor’s bid. When work is needed, the public entity will then issue a job order to the JOC contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Breach of Fiduciary Duty Claim Against Insurer Survives Motion to Dismiss
June 10, 2015 —
Tred R. Eyerly – Insurance Law HawaiiWhile some of their claims were dismissed, plaintiffs' breach of fiduciary duty survived the insurer's motion to dismiss. Senft v. Fireman's Fund Ins. Co., 2015 U.S. Dist. LEXIS 61870 (D. N.J. May 12, 2015).
Plaintiffs' waterfront home was insured by Fireman's Fund. Plaintiffs alleged that the broker represented that the policy would provide (1) coverage in the event of a hurricane,(2) the "highest level of protection" offered by Fireman's Fund, and (3) "exceptional" services in the event of a catastrophe. The policy included a 2% hurricane deductible because of the home's proximity to the ocean.
Hurricane Sandy badly damaged plaintiffs' home. Plaintiffs alleged that the winds from Sandy battered their home long before the storm surge reached the structure.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Mexico Architect Is Tuned Into His State
February 08, 2021 —
David M. Brown - Engineering News-RecordFor 40-plus years, Van Gilbert has combined his love for the topography, history and culture of New Mexico with an equally passionate dedication to designing not just structures, but buildings that help create communities.
Reprinted courtesy of
David M. Brown, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Overruling Henkel, California Supreme Court Validates Assignment of Policies
October 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a major ruling, the California Supreme Court applied a statutory provision to overrule its prior decision in Henkel Corp. v. Hartford Accident & Indemn. Co., 29 Cal. 4th 934 (2003) and ruled that liability policies can be assigned despite non-assignment provisions. See Fluor Corp. v. Superior Court, 2015 Cal. LEXIS 5631 (Cal. Aug. 20, 2015). The Hawaii Supreme Court relied on Henkel when it also found anti-consent provisions valid. See Del Monte Fresh Fresh Produce (Hawaii), Inc. v. Fireman's Fund Ins. Co., 117 Haw. 357, 183 P.3d 734 (2007) [see posts here and here].
For decades, Fluor Corporation performed engineering, procurement, and construction (EPC) operations through various corporate entities and subsidiaries. Beginning in 1971, Hartford issued up to 11 CGL policies to Fluor from 1971 to 1986. Each policy contained a consent-to-assignment clause reading: "Assignment of interest under the policy shall not bind the Company until its consent is endorsed hereon."
Beginning in the mid-1980s, Fluor Corporation was sued in numerous lawsuits claiming personal injury from asbestos exposure. Fluor Corporation tendered the early lawsuits to Hartford, which accepted the defense. Fluor Corporation subsequently went through a reverse spinoff under which a newly formed subsidiary, Fluor 2, took over the continuation of the company's EPC businesses. The original Fluor transferred all of its EPC-related assets and liabilities to Fluor-2, making Fluor-2 the parent of the EPC subsidiaries. The transaction did not except any insurance rights from the transfer of "any and all" assets.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Even Where Fraud and Contract Mix, Be Careful With Timing
April 12, 2021 —
Christopher G. Hill - Construction Law MusingsI have often discussed the limited circumstances under which a construction contract claim and a fraud claim can coexist. A recent case from the Western District of Virginia federal court demonstrates that care is necessary even in those limited circumstances.
In Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys., the Court examined the question of a fraud statute of limitations under Virginia law. The basic facts found in the Complaint are these:
In 2011, the United States Army awarded BAE Systems Ordinance Systems Inc. a basic ordering agreement under which BAE was responsible for modernization projects at the Radford Army Ammunition Plant. This action stems from a subcontract between Fluor Federal Solutions LLC and BAE, under which Fluor agreed to design and construct a new natural gas boiler at the plant. Fluor has completed work on the project, and BAE has accepted that work. Nonetheless, Fluor claims that BAE has refused or failed to pay for the balance of the project costs. Fluor alleges that BAE received several changes to its prime contract from the Army but did not pass those changes along to Fluor until after BAE solicited a bid from Fluor and entered a contract with Fluor to build a temporary facility. Instead, BAE continued to misrepresent the scope of the project. Fluor alleges that the change in plans increased costs substantially, but that BAE withheld information about those changes so that it could solicit lower bids. Fluor alleges that it requested a copy of BAE’s prime contract on numerous occasions, but BAE failed to provide a copy of it. Instead, Fluor submitted a request under the Freedom of Information Act. It received a copy of BAE’s prime contract on Oct. 3, 2018.