Supreme Court of Washington State Upholds SFAA Position on Spearin Doctrine
September 13, 2021 —
Peter Roth – The Surety & Fidelity Association of AmericaSeptember 9, 2021 (WASHINGTON, DC) –
The Surety & Fidelity Association of America (SFAA) commends the decision of The Supreme Court of The State of Washington to reverse the lower court ruling in the case of Lake Hills Investments, LLC vs. Rushforth Construction Co. As argued by SFAA, the Supreme Court found the contractor should not be responsible for damage caused by the defective design provided by the owner even where the contractor was responsible for certain defective work. In addition, the contractor is not completely barred from asserting this defense if the defects were caused by a combination of deficient performance by the contractor and deficient design, and proportional liability should be determined.
The SFAA, along with the National Electrical Contractors Association Puget Sound Chapter (NECA), Mechanical Contractors Association of Western Washington (MCAWW) and SMACNA-Western Washington (SMACNA), issued an Amici Curiae in support of Petitioner AP Rushforth Construction Co., Inc. d/b/a AP Rushforth, and Adolfson & Peterson, Inc.’s (collectively “AP”) Petition for Discretionary Review. In the brief they argued the Court should grant the Petition because the decision by the lower court is contrary to precedent of limiting a contractor’s liability when the owner’s defective plans and specifications caused the defective work, and upsets settled expectations of allocation of risk and liability between contractors, owners and architects (among others) on construction projects. This allocation of risk and the principle of limiting the contractor’s liability for defective work based on defective plans and specifications is long settled doctrine in Washington State and throughout the country, a doctrine based on the US Supreme Court’s landmark decision in U.S. vs. Spearin more than 100 years ago.
The Surety & Fidelity Association of America (SFAA) is a trade association of more than 425 insurance companies that write 98 percent of surety and fidelity bonds in the U.S. SFAA is licensed as a rating or advisory organization in all states and it has been designated by state insurance departments as a statistical agent for the reporting of fidelity and surety experience. www.surety.org
Read the court decisionRead the full story...Reprinted courtesy of
Peter Roth, SFAAMr. Roth may be contacted at
proth@surety.org
UK Construction Defect Suit Lost over One Word
October 16, 2013 —
CDJ STAFFIn the UK, be careful what you tell your insurer; the Court of Appeal has upheld the legality of basis clauses. As Paul Lewis and Janetta Gibbs of Herbert Smith Freehills LLP explain, “a basis clause is a provision set out in the proposal form or in the insurance contract itself, to the effect that all or any of the answers to the questions in the proposal shall form the basis of the contract of insurance.” The catch, as they point out, is that “should any of those answers — whether material to the risk or not — prove to be untrue, the insurer may repudiate the policy and treat itself as never having been on risk.” There is a move in the UK to abolish the use of basis clauses in business insurance, but currently they are still legal.
This came up in a construction defect case covering latent defects in a public housing project. The contract between the owner, Genesis Housing Association Limited, and the contractor, Time and Tide (Bedford) Ltd, required TT Bedford to indemnify Genesis if it became insolvent. In the contract with the insurer, representatives of Bedford and Genesis referred to the contractor as “TT Construction.”
While the courts concluded that Bedford and Genesis were not guilty of misrepresentation or intent to defraud, they did note that neither party thought the firm’s name was “TT Construction.” Therefore, over the failure to name the builder correctly, the court found that the insurance contract was invalid.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Termination Part 2: How to Handle Construction Administration When the Contractor Is Getting Fired
August 01, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaIf you’ve been working as a design professional for any length of time, you know that you must be a chameleon on the construction project. You need to “step into the skin” of both the Owner and the Contractor to determine who is at fault, and who should pay.
You are usually the Initial Decision Maker (IDM), and so you have a duty under the AIA documents to act fairly and impartially in making those decisions. See AIA B101§3.6.2.4.
Even if you are not under an AIA contract, you still have that duty if you are the IDM or handling construction administration for the project. More often than not, however, it will be the owner asking you to support its termination of the contractor “for cause.”
Should you do so?
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
‘Hallelujah,’ House Finally Approves $1T Infrastructure Funding Package
November 15, 2021 —
Tom Ichniowski - Engineering News-RecordAfter nearly three months in a holding pattern and a long day of back-and-forth negotiations among House Democrats, the chamber approved a sweeping, multi-year infrastructure funding package late on Nov. 5 that will provide an estimated $1 trillion for a wide range of infrastructure categories, including highways, transit, rail, water, power and broadband.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Appropriation Bill Cuts Military Construction Spending
June 15, 2011 —
CDJ STAFFThe Hill reports that HR 2055, the Military Construction, Veterans Affairs (VA) and Related Agencies bill, has passed with only five votes in opposition. The bill cuts the budget for military construction spending by $2.6 billion due to anticipated base closures.
The bill includes $186 million for family housing construction by the Army, $100 million for family housing construction by the Navy and Marines, and $84 million for family construction by the Air Force, with an additional $50 million allocated for the DOD outside the military branches. By the act, these funds will remain available until September 30, 2016.
Read the full story…
Read HR 2055
Read the court decisionRead the full story...Reprinted courtesy of
Wisconsin Court Enforces Breach of Contract Exclusion in E&O Policy
July 21, 2018 —
TLSS Insurance Law BlogIn its recent decision in Crum & Forster Specialty Ins. Co. v. GHD Inc.,2018 U.S. Dist. LEXIS 111827 (E.D. Wisc. July 5, 2018), the United States District Court for the Eastern District of Wisconsin had occasion to consider the application of a breach of contract exclusion in a professional liability policy.
Crum’s insured, DVO, was sued in connection with its contract to construct a biogas converter mechanism. The underlying suit alleged a sole cause of action; namely, breach of contract based on DVO’s failure to have fulfilled its obligations to design the mechanism to specification.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Straus & Shrewsberry LLP
Kansas City Airport Terminal Project Faces Delays, Rising Costs
February 06, 2019 —
Kansas City Star - Engineering News-RecordCosts have long since blown past initial estimates, prompting an independent review of the price tag. Its opening is eight months behind schedule and mounting delays drew heated questions from local officials last year.
Sounds like the continuing saga of Kansas City's planned airport terminal, overwhelmingly approved by voters in November 2017 . It's actually about the new international arrivals facility under construction at Seattle-Tacoma International Airport , or Sea-Tac.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at