Insurer's Motion to Dismiss Business Interruption, COVID-19 Claims Under Pollution Policy Fails
January 11, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer was unsuccessful in seeking to dismiss business interruption claims due to COVID-19 under a pollution policy. New York Botanical Garden v. Allied World Assur., 2021 N.Y. Misc. LEXIS 6012 (N.Y. Sup. Ct. Oct.15, 2021).
The insured was forced to cease operation after executive orders by the governor and mayor were issued in March 2020. The insured also had to reduce its in-person workforce by 100%. The insured's claim for business interruption and contingent business interruption were denied by Allied. The insured sued for a declaratory judgment.
Allied moved to dismiss, arguing that the executive orders were issued for prophylactic reasons in an effort to mitigate the spread of the virus. They were not issued solely to address the presence of COVID-19 at any non-insured owned location, but were issued broadly to limit the risk of spreading the COVID-19 virus. The insured responded that its broader pollution liability policy was not a typical civil authority policy that required the physical loss or damage to property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
While Construction Permits Slowly Rise, Construction Starts and Completions in California Are Stagnant
December 05, 2022 —
John Kazanovicz & Jason Feld - Kahana FeldThere is an interesting phenomenon happening in the California construction market since the Summer of 2022. There is a steady but slow rise in the construction building permits being issued throughout California. According to the U.S. Census and the U.S. Department of Housing and Urban Development’s joint announcement (https://www.census.gov/construction/nrc/pdf/newresconst.pdf) of new residential construction statistics for September 2022, privately‐owned housing units authorized by building permits in September were at a seasonally adjusted annual rate of 1,564,000. This is 1.4 percent above the revised August rate of 1,542,000. While this is slightly lower than a year ago (3.2 percent below the September 2021 rate of 1,615,000), the trend for obtaining new home permits was reportedly ahead of the projected rates given the market conditions and inflation throughout the country. Interestingly, single‐family authorizations in September were at a rate of 872,000 which was also 3.1 percent below the revised August 2022 figure of 900,000. Authorizations of units in buildings with five units or more were at a rate of 644,000 in September. Overall, while slowly recovering from the record lows during the height of the pandemic, the economic forecast for new home construction in California is positive, but cautious.
The flip side of this coin is the construction starts in California, which continue to remain stagnant despite additional building permits being issued. Privately‐owned housing starts in September were at a seasonally adjusted annual rate of 1,439,000. This is 8.1 percent (±14.9 percent) below the revised August estimate of 1,566,000 and is 7.7 percent (±11.5 percent) below the September 2021 rate of 1,559,000. Single‐family housing starts in September were at a rate of 892,000; this is 4.7 percent (±10.7 percent) below the revised August figure of 936,000. The September rate for units in buildings with five units or more was 530,000.
Reprinted courtesy of
John Kazanovicz, Kahana Feld and
Jason Feld, Kahana Feld
Mr. Kazanovicz may be contacted at jkazanovicz@kahanafeld.com
Mr. Feld may be contacted at jfeld@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Bert Hummel Appointed to Chief Justice’s Commission on Professionalism
May 10, 2021 —
Bert Hummel - Lewis BrisboisAtlanta Partner Bert Hummel was recently appointed to the Chief Justice’s Commission on Professionalism (CJCP) for the 2020-2021 term. In this role, Mr. Hummel has assisted in carrying out the charge of the CJCP, namely, to enhance professionalism among Georgia’s lawyers. Mr. Hummel’s appointment follows his participation on the Grants Committee and the Professionalism Committee of the CJCP. In addition, Mr. Hummel was selected as one of seven members of CJCP’s Benham Awards Subcommittee, which recognizes Georgia attorneys who dedicate their practice or time to serving the public and profession.
“I am honored to be appointed to a body that continually strives to do so much good for both the legal profession and the community at large. For the past several months, I have appreciated the work the Commission has undertaken to promote professionalism in the practice of law through educational programming while also promoting community service programs through the CJCP’s Grants Committee that I served on as well. I look forward to continuing to serve with my colleagues at the CJCP to promote our shared goals. I also relish the opportunity to serve during a time in which professionalism is of the utmost importance as we navigate through the COVID-19 pandemic made even more unique and special by the fact this is the last year Chief Justice Melton will serve as chair after announcing his retirement from the Supreme Court effective at the end of the Bar year.”
Read the court decisionRead the full story...Reprinted courtesy of
Bert Hummel, Lewis BrisboisMr. Hummel may be contacted at
Bert.Hummel@lewisbrisbois.com
Transportation Officials Make the Best of a Bumpy 2020
January 18, 2021 —
Jim Parsons & Aileen Cho - Engineering News-RecordThe year 2020 provided a bumpy budgetary ride for all modes of transportation, and some industry insiders don’t expect airport and transit ridership to return to pre-pandemic levels for years. Agencies are taking lessons learned, coupled with hopes for the new Biden administration, to carry on as best they can.
Reprinted courtesy of
Jim Parsons, Engineering News-Record and
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Colorado Supreme Court affirms Woodbridge II’s “Adverse Use” Distinction
December 20, 2021 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogLast year, I posted regarding the Colorado Court of Appeals’ decision in Woodbridge II, which concluded that the “adverse use” element for prescriptive easement claims only requires the claimant to “show a nonpermissive or otherwise unauthorized use of property that interfered with the owner’s property interests.” Viento Blanco, LLC, 2020 COA 34 (Woodbridge II), ¶ 2. Thus, Woodbridge II concluded, the claimants acknowledgement or recognition of an owner’s title alone is insufficient to defeat “adverse use” in the prescriptive easement context. Id. That decision was up for review by the Colorado Supreme Court at the time of my prior post. It has now been affirmed, thereby settling an arguable appellate decision split created by Woodbridge II. See Lo Viento Blanco, LLC v. Woodbridge Condo. Ass’n, Inc., 2021 CO 56 (“Woodbridge”).
“Like the division below, and for much the same reasons,” the Colorado Supreme Court affirmed in Woodbridge “that under Colorado law, a claimant’s acknowledgement or recognition of the owner’s title during the claimant’s asserted prescriptive period does not interrupt the prescriptive use or undermine the claimant’s adverse use.” Woodbridge, ¶ 2. Writing for a unanimous court, Justice Gabriel’s opinion agreed with the Court of Appeals’ reasoning “that although Woodbridge recognized that it did not hold title, no evidence indicated that it had acted in subordination to the owner’s title.” Id. ¶ at 13. The Court further agreed with Woodbridge II’srejection of Lo Viento’s “permissive use” argument because “the permission offered … was conditional and Woodbridge never agreed to any of the conditions set forth therein.” Id. On that basis, Woodbridge confirmed that “a claimant seeking to establish a prescriptive easement need not show that it asserted exclusive ownership of the property during the prescriptive period,” but only “that its use was without permission or otherwise unauthorized and that it interfered with the owner’s property interests.” Id. at ¶ 23.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
No Entitlement to Reimbursement of Pre-Tender Fees
April 28, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Federal District Court for the District of Hawaii determined that the insured was not entitled to pre-tender defense fees. The Hanover Ins. Co. v. Anova Food, LLC, 2016 U.S. Dist. LEXIS 38947 (D. Haw. March 24, 2016).
Anova sold and marketed fish. It was insured under policies issued by Hanover that covered claims of "personal and advertising injury."
A patent infringement and false advertising case was filed against Anova in the District Court for the District of Hawaii.The underlying complaint alleged Anova falsely, misleadingly, and deceptively advertised, promoted, and sold fish. The allegations covered a period of time between 1999 and 2012, a portion of which time Anova was covered by the Hanover policies.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Tips for Contractors Who Want to Help Rebuild After the California Wildfires
November 02, 2017 —
Garret Murai - California Construction Law BlogI received a call from one of my contractor clients this past week to see what he could do to help those affected by California’s North Bay fires.
The North Bay fires are the deadliest and most destructive wildfires in California’s history. To date, the fires have claimed 42 lives, burned more than 200,000 acres of land, destroyed an estimated 8,400 structures and likely damaged tens of thousands more. By comparison, the state’s second most deadly wildfire, the Oakland Hills fire of 1991, claimed the lives of 25 people, burned 1,600 acres of land, and destroyed 2,900 structures. Rebuilding costs for the North Bay fires, according to the California Insurance Commissioner, are expected to top $1 billion.
For those with insurance, insurance experts say that the rebuilding process can take two years or more for those whose homes and businesses were destroyed. For those whose homes and businesses were fortunate enough only to be damaged, rebuilding efforts are already underway.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
City of Birmingham Countersues Contractor for Incomplete Work
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in December of 2013, WVTM News reported that Chris Woods, a contractor, filed a lawsuit against the City of Birmingham, Alabama, demanding $1.5 million for the West Police Precinct and two other projects he had been contracted on. However, “Birmingham claimed Woods was fired for not completing projects on time and other contract breaches.”
On March 7th, WVTM News reported that the City of Birmingham has filed a counterclaim against Woods, alleging that he “owes $1.2 million for incomplete work.” The city listed his “inability to meet specific construction deadlines and finish either project on time as factors for his termination.” Woods, however, blamed the city for delays, citing multiple design changes requested by Birmingham.
The city’s counterclaim also alleged that “Star Insurance Company, ‘identified major, numerous defects in the work that Woods had performed prior to the termination of the West Precinct Project.’”
Read the full story, December 2013 Article...