You Cannot Arbitrate Claims Not Covered By The Arbitration Agreement
March 16, 2020 —
David Adelstein - Florida Construction Legal UpdatesRegardless of the type of contract you are dealing with, “[a]rbitration provisions are contractual in nature, and therefore, construction of such provisions and the contracts in which they appear is a matter of contract interpretation.” Wiener v. Taylor Morrison Services, Inc., 44 Fla. L. Weekly D3012f (Fla. 1st DCA 2019). This means if you want to preserve your right to arbitrate claims you want to make sure your contract unambiguously expresses this right. Taking this one step further, if you want to make sure an arbitrator, and not the court, determines whether the claim is arbitrable if a dispute arises, you want to make sure that right is expressly contained in the arbitration provision.
For example, in Wiener, a homeowner sued a home-builder for violation of the building code – a fairly common claim in a construction defect action. The homeowner’s claim dealt with a violation of building code as to exterior stucco deficiencies. The home-builder moved to compel the lawsuit to arbitration based on a structural warranty it provided to the homeowner that contained an arbitration provision. The structural warranty, however, was limited and did not apply to non-load-bearing elements which, per the warranty, were not deemed to have the potential for a major structural defect (e.g., a structural defect to load-bearing elements that would cause the home to be unsafe or inhabitable). The trial court compelled the dispute to arbitration pursuant to the arbitration provision in the structural warranty.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
State Farm Too Quick To Deny Coverage, Court Rules
July 22, 2011 —
CDJ STAFFOn July 13, 2011, Judge Sarah S. Vance of the US District Court issued a rule in the case of Travelers Cas. & Surety Co. of Am. v. Univ. Facilities, Inc. (E.D. La., 2011). In this case, Stanley Smith Drywall was contracted by Capstone Building Corporation to “perform undisclosed work at the facility believed to involve the installation of drywall.” The project involved the design and construction of student residences for the Southeastern Louisiana University in Hammond, Louisiana. In May, 2009, University Facilities, Inc. (UFI) sued Capstone Development Corporation and Capstone On-Campus Management.
State Farm insured Stanley Smith Drywall and they sought a declaration that they have no duty: “(1) to insure Stanley Smith or CBC, or (2) to defend or indemnify any party against UFI's claims in the pending arbitration.” State Farm contends “(1) there is no "occurrence" to trigger coverage under the policy; (2) only breach of contract claims are asserted; (3) there is no property damage alleged; and (4) various coverage limitations and exclusions apply to prevent coverage.’
The court concluded that “whether State Farm has a duty to defend in the arbitration must be determined by considering the claims asserted in the arbitration.” However, the arbitration claims were not made part of the record. There, “, the Court cannot determine as a matter of law State Farm's duty to defend on the present record.” The same was true of State Farm’s duty to indemnify. “Stanley Smith and CBC assert that State Farm's motion for summary judgment was filed before any discovery was conducted in the arbitration proceeding or in this case. The Court finds that State Farm has failed to develop the record sufficiently to establish that there is no genuine issue of material fact as to its duty to indemnify Stanley Smith or CBC in the arbitration.’
The court denied State Farm’s motion for a summary judgment on its duty to defend and indemnify.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
GE to Repay $87 Million for Scaled-Back Headquarters Plan
February 27, 2019 —
Rick Clough - BloombergGeneral Electric Co. will reimburse the state of Massachusetts for funds used to develop the manufacturer’s future headquarters, a project that is now being scaled back under Chief Executive Officer Larry Culp.
GE and the state will jointly sell the property in Boston’s Fort Point neighborhood where the company will make its future home, according to an agreement revealed Thursday. GE still plans to move into the campus later this year -- as a tenant rather than owner -- but it’s scrapping plans to build an adjacent 12-story tower.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Clough, Bloomberg
Although Property Damage Arises From An Occurrence, Coverage Barred By Business Risk Exclusions
July 08, 2011 —
Tred R. Eyerly - Insurance Law HawaiiThe homeowners hired the insured to raise the structure of their home twenty-four inches above the flood zone. Lafayette Ins. Co. v. Peerboom, 2011 U.S. Dist. LEXIS 58985 (S.D. Miss. June 2, 2011). When the insured’s crew returned from lunch one day, they found the house had fallen from hydraulic jacks being used to raise the structure a few inches at a time. There was substantial damage to the entire structure.
The homeowners sued, asserting several claims, including negligence and breach of contract. The complaint alleged the homeowners entered a contract with the insured to raise their structure while maintaining its integrity. However, the insured failed to use proper equipment, which caused the house to fall and be completely destroyed.
The insured tendered the claim to its insurer, Lafayette Insurance Company. Lafayette defended under a reservation of rights and filed suit for a declaratory judgment. Lafayette’s subsequent motion for summary judgment contended there was no “occurrence” alleged in the underlying complaint and, even if there was, the business risk exclusions barred coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Problems May Delay Bay Bridge
May 10, 2013 —
CDJ STAFFFaulty bolts could lead to a delay in the opening of the Bay Bridge. Caltrans noticed problems with bolts and found that the bolts had cracked. Of the 98 bolts already tightened, 30 have failed. According to the San Francisco Chronicle, workers will be tightening all 288 bolts and then testing them. According to Tony Anziano, Caltrans’s toll bridge program manager, repairs could take one or two months. Mr. Anziano noted that the manufacturer might be responsible for part of the expense, but that the budget for the bridge also has funds set aside for unanticipated repairs.
The bolts were supplied by Dyson, an Ohio company, but it was clear whether Dyson manufactured the bolts or simply marketed them.
Read the court decisionRead the full story...Reprinted courtesy of
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Los Angeles Could Be Devastated by the Next Big Earthquake
October 15, 2013 —
CDJ STAFFA group of scientists have made a list of about 1,500 concrete buildings in Los Angeles which could potentially collapse in an earthquake. They have offered to make the list available to Los Angeles officials, although the city has yet to take them up on the offer. In response, a group of Times reporters combed through records to identify which buildings were of the sort most likely to collapse in an earthquake. The group found more than 1,000 concrete buildings built before 1976 when Los Angeles increased the requirements for steel rebar.
Experts estimate that in a major earthquake, five percent of these buildings could collapse, which for Los Angeles would mean about 50 buildings. Many of these buildings could be seismically retrofitted, but the article notes that a retrofit starts with a $100,000 structural study. Carol Schatz of the Central City Association notes that the cost of retrofitting “would be greater than the value of the building.”
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Supreme Court Rules Matching of Materials Decided by Appraisers
March 28, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Connecticut Supreme Court determined that an appraisal panel could resolve whether the insurer must replace undamaged materials so that they match the damaged materials. Klass v. Liberty Mut. Ins. Co., 2022 Conn. LEXIS 2 (Conn. Jan. 11, 2022).
The insured reported damage to the roof of his home to Liberty Mutual. A representative from Liberty Mutual inspected and noticed a few shingles missing from the rear slope of the roof. The representative agreed that the damage was caused by wind damage, a covered loss under the policy. Liberty Mutual accepted coverage and issued an estimate to replace the rear slope of the roof. The insured's contractor inspected the roof and provided an estimate that contemplated replacement of the entire roof at nearly double the cost of Liberty Mutual's estimate.
The insured requested an appraisal. Liberty Mutual responded that the insured could not invoke the appraisal process in the absence of a "competing" estimate (i.e., one that addressed the claim for which coverage was accepted). Any dispute regarding the matching of the front and rear roof slope was a question of coverage, not an issue for appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com