Supreme Court Holds Arbitrator can Fully Decide Threshold Arbitrability Issue
March 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe United States Supreme Court recently decided parties to a contract can agree, under the Federal Arbitration Act, an arbitrator, rather than a court, can fully resolve the initial arbitrability question. Henry Schein, Inc. v. Archer and White Sales, Inc., 2019 WL 122164 (2019). The arbitrability question is whether the dispute itself is subject to arbitration under an arbitration provision. Parties that do not want to arbitrate try to circumvent this process by filing a lawsuit and asking the court to determine the threshold arbitrability question.
In Henry Schein, Inc., the contract at-issue provided:
This Agreement shall be governed by the laws of the State of North Carolina. Any dispute arising under or related to this Agreement (except for actions seeking injunctive relief and disputes related to trademarks, trade secrets, or other intellectual property) shall be resolved by binding arbitration in accordance with the arbitration rules of the American Arbitration Association. The place of arbitration shall be in Charlotte, North Carolina.
The plaintiff in this case asserted a claim for injunctive relief (among other claims) and argued that, therefore, the dispute is not subject to arbitration based on the exception in the provision. The initial, threshold issue became whether the dispute was subject to arbitration and, importantly, who decides this issue. The Court further looked at whether a trial court can resolve this issue under the “wholly groundless” exception, i.e.,the court can decide the issue if the argument for arbitration is wholly groundless.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
No Coverage for Installation of Defective Steel Framing
June 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal affirmed the trial court's holding that the insurer had no duty to defend claims arising out of the insureds' installation of defective steel framing in an apartment building. Regional Steel Corp. v. Liberty Surplus Ins. Corp., No. B245961(Cal. Ct. App. May 16, 2014) [decision here].
Regional Steel was a subcontractor for providing reinforced steel to the columns, walls, and floors of an apartment building under construction. Regional used 90 degree and 135 degree seismic hooks as approved by the general contractor, JSM Construction, Inc. The City building inspector issued a correction notice, however, requiring the exclusive use of the 135 degree hooks. Levels one through three had defective tie hooks and required repair. JSM refused to pay Regional's invoices and withheld $545,000. JSM had to make repairs that required opening up numerous locations in the concrete walls, welding reinforcements to the steel placed by Regional, and otherwise strengthening the inadequate installation.
Regional sued JSM for the withheld payment. JSM cross-claimed, asserting breach of contract and breach of express and implied warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Colorado Construction Defect Reform Act Explained
December 11, 2013 —
CDJ STAFFColorado passed its Construction Action Defect Reform Act twelve years ago, but as Anne K. McMichael of Zupkus & Angell, PC, points out, “while portions of this act are reasonably straightforward, several of the sections are subject to ongoing debate as to how these concepts should be applied to achieve fair and unbiased results.” The process for a construction defect claim under the CDARA starts with filing a notice of defects, after which the construction professional is permitted to inspect the alleged defect. The construction professional can then offer to repair or settle.
The law offers protections for construction professionals who follow through with the process. But, as Ms. McMichael notes, these are denied to construction professionals who do not make offers, fail to meet settlement agreements, or offers a settlement that is insufficient for repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Predicting Our Future with Andrew Weinreich
May 03, 2017 —
Aarni Heiskanen - AEC BusinessIn this podcast episode, my guest is Andrew Weinreich. We talk about the future of homebuilding against the backdrop of Andrew’s new podcast Predicting Our Future.
Is construction ripe for disruption? Andrew believes that homebuilding is much closer to a tipping point than ever before. In this interview, he explains why.
“In the United States, modular construction significantly lags behind what we see elsewhere around the world,” Andrew reminds. “When everything you can imagine today, from the paperclip to your smartphone is made in a factory, why is it that -certainly in this country- we associate homes made in factory with the lowest of low end homes.”
“The first question is: why is that? And the second question is: could that change? Could we be on the precipice of looking at the next Tesla; not for car-building, but for homebuilding.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Meet the Forum's ADR Neutrals: LESLIE KING O'NEAL
January 29, 2024 —
Marissa L. Downs - The Dispute ResolverCompany: JAMS
Office Location: Orlando, FL
Email: lkoneal1117@gmail.com
Website: https://www.jamsadr.com/oneal/
Law School: University of Florida, J.D. (1977)
Types of ADR services offered: Mediation, arbitration, neutral evaluation
Geographic area served: Nationwide
Q: Describe the path you took to becoming an ADR neutral.
A: Florida was one of the first states to allow judges to send civil cases to mediation. When I was an advocate, nearly all my cases went to mediation at least once—sometimes more than once! I became a firm believer in the value of mediation and other ADR methods. I became a Florida certified circuit court mediator in 2021 and I joined JAMS in 2022, after retiring as in-house counsel with Brasfield & Gorrie, a large commercial general contractor. I am also an adjunct professor at Pepperdine Law School, teaching arbitration theory and practice in its master of dispute resolution and master of laws programs.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
General Contractor Intervening to Compel Arbitration Per the Subcontract
December 06, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is not uncommon that a general contractor’s subcontract will include an arbitration provision. Or it will allow the general contractor to select binding arbitration as the method to resolve disputes at the general contractor’s SOLE OPTION. A general contractor’s subcontract should absolutely give the general contractor this important right. (Keep this in mind when drafting dispute resolution provisions for a general contractor.)
It is also not uncommon for a subcontractor the sue a general contractor’s payment bond surety, and NOT the general contractor. One reason to do this is to create an argument to avoid the dispute resolution provision in the subcontract. (Another reason is to avoid any pay-if-paid defense.) When this occurs, a general contractor may still want to arbitrate the subcontractor’s payment bond dispute and a way to do so is for the general intervene in the lawsuit and move to compel arbitration. Sometimes, it is even practical for the general contractor to immediately initiate the arbitration process against the subcontractor, particularly if the general contractor wants to assert a counterclaim, so that the motion to compel is supported by the formal demand for arbitration (and filed with the American Arbitration Association or other body administering the arbitration). I have done this on a number of occasions.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Is Your Design Professional Construction Contract too Friendly? (Law Note)
July 09, 2014 —
Melissa Dewey Brumback – Construction Law North CarolinaMy husband often travels the back roads between Chapel Hill and Fuquay Varina to visit friends. En route (a circuitous route that goes past Sharon Harris Nuclear Power Plant, among other places), he passes by the “Friendly Grocery.”
[Sign]
No *Loitering*Littering*Alcoholic Beverages on Premises*Bike*Skateboard*
*10 minutes Parking Limit*Towing Enforced*
I’m not sure which is the “friendly” part of that sign. In fact, the sign seems to be the antithesis of friendly.
What does this have to do with your construction contracts? Sometimes, in an effort to please the client and/or secure the project, architects and engineers have the habit of being too friendly in their contract language. That is, you make promises or proposals that may promise too much of a good thing for the client. This can cause big problems. Bigger than being towed away from a rural grocery store in the middle of nowhere. You could be putting your insurance coverage at risk.
Have you ever promised to use “best efforts” in your design or plans? Promised to design to a specific LEED standard? Guaranteed 100% satisfaction? You might be putting your errors & omission coverage at issue. By warrantying or guaranteeing something, you are assuming a level of liability well beyond the standard of care required by law. By law, you only need to conform to the standard of care, and your insurance will only provide coverage up to that standard of care. In other words, if you make guarantees or promise “best efforts,” you are contracting to something that will *not* be insured. If something goes wrong, you will be without the benefit of your professional liability coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Fast-Moving Isaias Dishes Out Disruption in the Mid-Atlantic, Northeast
August 24, 2020 —
Jim Parsons - Engineering News-RecordFar from the most powerful storm to strike the Eastern Seaboard, Hurricane Isaias nevertheless proved disruptive enough to rival some infrastructure impacts from Superstorm Sandy in 2012 while also raising concerns about the potential of additional doses of destruction arriving in the coming months.
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of